You are the program manager for the GHT Program for your company. This program has a budget at completion of $789,000 and is currently 40 percent complete, though it was scheduled to be 50 percent at this time. Your program has spent $325,000 of the budget to date. Based on this information, how many pennies is your program losing per dollar spent on the work?

LEAVE A REPLY

Your email address will not be published. Required fields are marked *

Question List (200q)
Question 1: Paula is program manager for her organization. It has come t...
Question 2: A program receives initial approval from the selection commi...
Question 3: The Project Manager is creating an estimate for building a c...
Question 4: A program manager is identifying and verifying risks as outl...
Question 5: A program with objectives that impact a large segment of the...
Question 6: You are trying to determine if you should buy or build a sol...
Question 7: A Project Manager has been working on quality process of a p...
Question 8: A program manager assigns project managers to five component...
Question 9: A program manager is working with the sponsor, stakeholders,...
Question 10: Which of the following is described in the statement given b...
Question 11: A program manager has a multiple-project program that is sch...
Question 12: A program is in its last year of execution. The program mana...
Question 13: The project will be using a company to provide the technicia...
Question 14: What does RACI stand for?
Question 15: A company is releasing a new product geared toward a specifi...
Question 16: What quality control chart compares two or more variables ov...
Question 17: You are the program manager for your organization. As your p...
Question 18: A rapidly expanding IT company wants to mature its delivery ...
Question 19: After a company's senior executive management meeting, the C...
Question 20: What is a stakeholder analysis chart?...
Question 21: A hotel chain initiates a program to expand meeting offering...
Question 22: You are a Project Manager managing the building of a housing...
Question 23: The chief executive officer reminds a program manager that a...
Question 24: Alice is the project manager of the NHQ Project and is enter...
Question 25: A design and production company's program comprises the desi...
Question 26: You are the program manager for your organization and are pl...
Question 27: You are the program manager for your organization. Managemen...
Question 28: Which of the following shows the ratio between a task's budg...
Question 29: Which of the following terms is used for a schedule compress...
Question 30: Ben is the program manager for his organization. He's workin...
Question 31: Molly is the program manager for her organization. She is cr...
Question 32: As a Program Manager, you decide to take the team on an outi...
Question 33: You are the program manager for your organization. One of th...
Question 34: You need to create a document that will define the costs, re...
Question 35: Kelly's program is slipping on its schedule. Management is w...
Question 36: At the beginning of the second year of a five-year strategic...
Question 37: Mary Anne is the program manager for her organization. In he...
Question 38: A natural disaster shuts down operations for two days. The p...
Question 39: You are the program manager for your organization that utili...
Question 40: A program governance board mandates that phase gate reviews ...
Question 41: Leigh is working with the project stakeholders to define the...
Question 42: A program has a budget at completion of $1,250,000 and has a...
Question 43: Which of the following can be used to help you or other proj...
Question 44: A program manager for the construction of an international e...
Question 45: You are the program manager for your organization and you ar...
Question 46: You are the program manager for your organization. Your prog...
Question 47: The program manager compiles a program performance report fo...
Question 48: A program manager is responsible for constructing a US$50 mi...
Question 49: What is the primary purpose of a project kick-off meeting?...
Question 50: A program manager, who reports to a company's CIO, is respon...
Question 51: A company CEO issues a mandate to automate a new-client onbo...
Question 52: In the last year, all program phase gate reviews received ex...
Question 53: The Project Manager and team are planning a banking software...
Question 54: An organization is considering a new program. The business a...
Question 55: While setting up a program's infrastructure and plan, a prog...
Question 56: Terri is the program manager for her organization and she's ...
Question 57: As a Project Manager you have a professional and social resp...
Question 58: An aircraft manufacturer is engaged by an airline to build a...
Question 59: You are the program manager of the NHQ Program. You are work...
Question 60: Julie is the project manager of the NHQ Project. She and her...
Question 61: Hal is the program manager for his organization. He would li...
Question 62: A program manager prepares the program for review to secure ...
Question 63: Martha is sharing her experience of her last project as the ...
Question 64: A Project Manager has been assigned to manage a project that...
Question 65: The Project Manager is ordering cables for the video board h...
Question 66: Which of the following contract types is described in the st...
Question 67: You are the program manager for a construction program. In t...
Question 68: Complete the following phrase about quality management: Qual...
Question 69: What schedule analysis simulation tool allows you, the proje...
Question 70: Which of the following represents the duration of activities...
Question 71: You are the project manager of a construction project. You h...
Question 72: A project manager in your program has estimated the cost of ...
Question 73: You are in the process of purchasing 67 desktop computers, m...
Question 74: You are the program manage of HYH Program for your organizat...
Question 75: The project managers for component projects A and B schedule...
Question 76: You are the program manager for a new software development p...
Question 77: You are the program manager for your organization and are re...
Question 78: An organization initiates an innovation program to deliver e...
Question 79: Which of the following documents provides the mandate to exe...
Question 80: You are the program manager for your organization and your t...
Question 81: A company's marketing department fails an internal complianc...
Question 82: You are a Project Manager who is involved in the procurement...
Question 83: Which of the following directs the improvement efforts to th...
Question 84: In your program you must adhere to Six Sigma as part of your...
Question 85: The above performance report shows the earned value (EV) ana...
Question 86: You are a program manager for an environmental program. The ...
Question 87: A program manager for an electronic gaming manufacturer is m...
Question 88: A program manager has been assigned to a program that has re...
Question 89: You are the project manager for the JJY Project, which is si...
Question 90: A program includes the development and shipping of 12 millio...
Question 91: An organization is embarking on a new program aligned with i...
Question 92: The team has implemented a risk response plan when a vendor ...
Question 93: Which of the following best relates to unknown unknowns?...
Question 94: After taking over a program, a program manager reviews the p...
Question 95: You are the program manager for your organization. You are e...
Question 96: A program in a matrix organization includes subprojects for ...
Question 97: On the electric company project the government implemented a...
Question 98: A sponsor decides that the business environment is unfavorab...
Question 99: You are a program manager for a large construction program. ...
Question 100: You are the program manager for your organization. A new pro...
Question 101: The chief executive officer (CEO) informs the program manage...
Question 102: During the last steering committee meeting, a program manage...
Question 103: A program manager evaluates conflicting stakeholder demands ...
Question 104: You are the program manager for your organization and are wo...
Question 105: A program manager is concerned that a program will be unable...
Question 106: A software company's program manager is conducting closing p...
Question 107: A program manager is appointed to manage a new program. The ...
Question 108: You are the program manager for your organization. Part of y...
Question 109: You are the program manager for the GHT Program for your com...
Question 110: You are the program manager for your organization and are wo...
Question 111: Program management has several themes that the program manag...
Question 112: An experienced program manager is leading a development prog...
Question 113: Status information, including program and component status, ...
Question 114: You are the Project Manager for a national satellite rollout...
Question 115: Your program creates a byproduct that you could sell to a cl...
Question 116: Harriet is the program manager of a large program that has a...
Question 117: You are the program manager for your organization and you're...
Question 118: The program sponsor requests a weekly performance report. Th...
Question 119: Mike is the program manager of the NHQ Program. Mike and a v...
Question 120: Which of the following statements is the most accurate when ...
Question 121: Which of the following types of floats are available? Each c...
Question 122: You are a Project Manager managing the building of a restaur...
Question 123: The program director of a four-year program, estimated to re...
Question 124: A program manager has four projects pending approval. Senior...
Question 125: The program manager of a multinational program must reconcil...
Question 126: All of the following are reasons for outsourcing work except...
Question 127: What does CPI value less than 1.0 indicates?...
Question 128: Which of the following plans should a project manager implem...
Question 129: You are a program manager of a program. You are required to ...
Question 130: An initiative involves the development of new technology and...
Question 131: You are the project manager for the GGG Project and are abou...
Question 132: Your company is evaluating two projects for consideration. P...
Question 133: A program delivers incremental benefits, but is far from clo...
Question 134: Andy is the program manager of the HQN Program. This program...
Question 135: You are the program manager for your organization and are pl...
Question 136: You are the program manager of the NHQ Program. You will nee...
Question 137: Your program has been selected and its program charter is no...
Question 138: A program manager concurrently implements a software program...
Question 139: Component project managers create project management plans f...
Question 140: Where are negative risks recorded?...
Question 141: You are the program manager for the BHN Program. Your progra...
Question 142: Molly is the program manager for her organization and she is...
Question 143: What percentage of communication is nonverbal?...
Question 144: The contract is expected to cost $280K US. Actual costs are ...
Question 145: You are the program manager for your organization. Your prog...
Question 146: To meet growth expectations and its board's mandate, an orga...
Question 147: A company wants to perform a preliminary stakeholder analysi...
Question 148: A Project Manager has been working on quality process of a p...
Question 149: A multi-year complex program will deliver advanced driver as...
Question 150: A program with 10 components is in the planning phase. Proje...
Question 151: Your company and a competing company have created a teaming ...
Question 152: Which of the following can be an effective tool during quali...
Question 153: A program manager at a pharmaceutical company plans a new dr...
Question 154: The Crosswind broadcasting has recently been awarded a large...
Question 155: A program manager takes over a global program from another p...
Question 156: You have created a control chart for a repeatable process in...
Question 157: You are the program manager for your organization. Your prog...
Question 158: You have identified several issues in your program and have ...
Question 159: A project manager in your program is using progress elaborat...
Question 160: A team member has made a mistake during the installation of ...
Question 161: You are managing a project and the sponsor has removed the p...
Question 162: You are the program manager of the HNG Program. This program...
Question 163: Your program has a budget at completion of $1,550,000 and is...
Question 164: Which of the following would a Contract Administrator use if...
Question 165: Which one of the following is the best example of transferen...
Question 166: Stakeholders make ad-hoc requests on a routine basis. This c...
Question 167: A project you have been managing is falling behind schedule....
Question 168: Julie is the program manager of the NHQ Program for her orga...
Question 169: Small changes that bypass the organization's change control ...
Question 170: Paul is the program manager for his company. He along with h...
Question 171: After program closure, the lessons learned document becomes ...
Question 172: A global enterprise resource planning (ERP) program's scope ...
Question 173: The program sponsor returns from a board of directors meetin...
Question 174: A program to implement a new payroll processing system at a ...
Question 175: A three-year program using vendor contracts, incorporating r...
Question 176: You are the program manager for your organization and are wo...
Question 177: The program charter for a new, five-component program has be...
Question 178: How does a portfolio's collection of work differ from that o...
Question 179: A program manager is working on benefits. The program team c...
Question 180: A program manager is leading a program to transform an organ...
Question 181: You are the program manager of the MQQ Program. Your program...
Question 182: You are the program manager of the NHQ Program. The program ...
Question 183: Your program has just been chartered during the program init...
Question 184: You are the program manager for your organization. Your curr...
Question 185: Which one of the following is not an output of the direct an...
Question 186: You are the program manager for your organization and are co...
Question 187: What is the formula to determine earned value (EV) for a pro...
Question 188: A two-year program is coming to an end. Many of the initial ...
Question 189: A global financial system is being delivered by the program ...
Question 190: The program manager wants to ensure that a program contribut...
Question 191: A program is developing a next-generation product line, and ...
Question 192: At what point in the project is the risk of failing to achie...
Question 193: You are the program manager of the GHY Program in your organ...
Question 194: A new program is being initiated for the HNQ Organization. T...
Question 195: You are the owner of a house painting company. You occasiona...
Question 196: You are the program manager for your organization and you ar...
Question 197: Ranking risks is performed in which of the following?...
Question 198: Which of the following risk response planning techniques is ...
Question 199: You work as a program manager for a large construction progr...
Question 200: You are the program manager for your organization and are wo...