Valid PgMP Dumps shared by ExamDiscuss.com for Helping Passing PgMP Exam! ExamDiscuss.com now offer the newest PgMP exam dumps, the ExamDiscuss.com PgMP exam questions have been updated and answers have been corrected get the newest ExamDiscuss.com PgMP dumps with Test Engine here:
The program manager compiles a program performance report for review by the program governance board. The performance report indicates that the scope, quality, and schedule objectives have been met, but costs and resource utilization are higher than expected. The program can no longer deliver the planned return-on- investment within an acceptable level and the intended benefits have not yet been realized. After further analysis of the performance indicators, the program manager should do which of the following?