Question 47/159

You are program manager for the HYH Program. Your program governance is requiring you to use earned value management to predict how closely your program is tracking to the cost and schedule baselines and to predict overall program performance. Which earned value management formula can you use to predict how much more will need to be invested in the program based on current program performance?

LEAVE A REPLY

Your email address will not be published. Required fields are marked *

Question List (159q)
Question 1: Which of the following can be used to help you or other proj...
Question 2: You are the program manager for your organization. Managemen...
Question 3: Which of the following is used to build consensus through ro...
Question 4: Which of the following statements are true regarding program...
Question 5: You are the program manager of the BHG Program. One of the p...
Question 6: If a risk has a probability of 60 percent and an impact of -...
Question 7: An unforeseen geopolitical risk impacts a program to establi...
Question 8: You are the program manager of the HNG Program. This program...
Question 9: All of the following are benefits of a program except for wh...
Question 10: A program has a BAC of $550,000 and is currently 45 percent ...
Question 11: Your company and a competing company have created a teaming ...
Question 12: A program completes all component projects and all identifie...
Question 13: A program is in its last year of execution. The program mana...
Question 14: You are the program manager for your organization. You have ...
Question 15: Rick is a Program Manager for a large construction program. ...
Question 16: You are the program manager of HYH Program for your organiza...
Question 17: What component of the change management system is responsibl...
Question 18: You need to create a document that will define the costs, re...
Question 19: Which one of the following is not considered one of the thre...
Question 20: What quality control chart compares two or more variables ov...
Question 21: You are the program manager for your organization and your t...
Question 22: Your program has just been chartered during the program init...
Question 23: A program with objectives that impact a large segment of the...
Question 24: You are the program manager for the GHT Program for your com...
Question 25: You are the program manager of the YHT Program. You have bee...
Question 26: You are the program manager of the YGH Program. A vendor has...
Question 27: A risk response in a project in your program has actually ca...
Question 28: A multi-year complex program will deliver advanced driver as...
Question 29: You are the program manager for your organization. You're cu...
Question 30: Robert's program is slipping on its schedule and management ...
Question 31: Which of the following represents the duration of activities...
Question 32: A program manager at a pharmaceutical company plans a new dr...
Question 33: A component project of a multiyear program delivers all expe...
Question 34: You are the program manager for your organization. Managemen...
Question 35: Which of the following can be an effective tool during quali...
Question 36: Which of the following contract types is described in the st...
Question 37: A company hires a program manager to create a healthcare man...
Question 38: During the program execution stage, the component project ma...
1 commentQuestion 39: A program manager initiates a new global program to create a...
Question 40: After a company's senior executive management meeting, the C...
Question 41: Which of the following plans should a project manager implem...
Question 42: Which of the following shows the ratio between a task's budg...
Question 43: Wanda is the program manager for her organization. Her progr...
Question 44: You are a program manager for a large construction program. ...
Question 45: A key stakeholder's requirement contradicts the organization...
Question 46: You are the program manager of the NQA Program. In this prog...
Question 47: You are program manager for the HYH Program. Your program go...
Question 48: Gina is the program manager for her organization and is revi...
Question 49: A program is in its execution phase when a component project...
Question 50: Which of the following tools and techniques are parts of the...
Question 51: Leigh is working with the project stakeholders to define the...
Question 52: After meeting with the program sponsor and stakeholders, the...
Question 53: Who makes Go/No-Go decisions during phase gate reviews?...
Question 54: Kelly's program is slipping on its schedule. Management is w...
Question 55: Which of the following documents sets the project objectives...
Question 56: You are the program manager for your organization. Managemen...
Question 57: Over the life of your program you've received many change re...
Question 58: You are the program manager of the HNG Program. This program...
Question 59: During program execution, how does a program manager ensure ...
Question 60: During a program's definition phase, it is determined that t...
Question 61: Throughout a multiyear program, component projects are trans...
Question 62: A country is in the process of strengthening its defense pro...
Question 63: A component project of a program is completed, and will prov...
Question 64: A two-year program is coming to an end. Many of the initial ...
Question 65: A program manager is working with the sponsor, stakeholders,...
Question 66: Don is the project manager of the NQP Project for his organi...
Question 67: Which of the following documents describes the details for e...
Question 68: You are the program manager for your organization and manage...
Question 69: You are the program manager for your organization. You and y...
Question 70: You are the program manager for your organization and are re...
Question 71: Donna is the project manager for her organization. She is pr...
Question 72: The program manager defines the program objectives, requirem...
Question 73: Your program has a budget at completion of $1,550,000 and is...
Question 74: You are the program manager for your organization and you're...
Question 75: Thequality assurance technique ensures continuous improvemen...
Question 76: At what point in the project is the risk of failing to achie...
Question 77: Holly is the program manager for her program. She is creatin...
Question 78: You are the program manager of the MQQ Program. Your program...
Question 79: Stakeholders make ad-hoc requests on a routine basis. This c...
Question 80: You are the program manager for your program and are creatin...
Question 81: Which of the following terms is used for a schedule compress...
Question 82: In which of the following processes is the program charter c...
Question 83: A program manager has four projects pending approval. Senior...
Question 84: The new performance financial system is delivered to all bus...
Question 85: You are the project manager for the GGG Project and are abou...
Question 86: You are the program manager for your organization and are wo...
Question 87: The program manager has a global program with five component...
Question 88: You are the program manager for your organization. Your curr...
Question 89: You are the program manager for your organization and you ar...
Question 90: Which one of the following is the best example of transferen...
Question 91: A program will generate revenue for several years after it e...
Question 92: A large program consists of several component projects and s...
Question 93: Your program has 121 stakeholders that you'll need to commun...
Question 94: Complete the following phrase about quality management: Qual...
Question 95: You are the program manager for your organization and workin...
Question 96: You are coaching Tammy, a project manager in your program, o...
Question 97: You are the program manager for a construction program. In t...
Question 98: A program is midway through the program delivery phase when ...
Question 99: A newly appointed country manager suggests that the regional...
Question 100: You are the program manager for your organization. One of th...
Question 101: You are the program manager of the NHQ Program. You are work...
Question 102: Ben is the program manager for his organization. He's workin...
Question 103: You are the program manager for your organization and are wo...
Question 104: Wan is the program manager for his organization. He has been...
Question 105: Your program will create new software and install new hardwa...
Question 106: A company is releasing a new product geared toward a specifi...
Question 107: Which of the following documents contain a list of all probl...
Question 108: The project managers for component projects A and B schedule...
Question 109: During the selection of source process, you assign certain p...
Question 110: You are the program manager for your organization. You have ...
Question 111: The number of emerging risks increases in a component projec...
Question 112: You are the program manager for your organization. Your curr...
Question 113: An IT program manager is concerned that a program is not ach...
Question 114: You are the program manager for a large program in your matr...
Question 115: A program governance board mandates that phase gate reviews ...
Question 116: What schedule analysis simulation tool allows you, the proje...
Question 117: You are the program manager for the SRQ Program. You have re...
Question 118: A global enterprise resource planning (ERP) program's scope ...
Question 119: You are hosting a meeting with all of the vendors that have ...
Question 120: In preparation for the development and submission of the pro...
Question 121: A program receives initial approval from the selection commi...
Question 122: Your program is to construct a new condo building in Chicago...
Question 123: You are the program manager for your organization. Your prog...
Question 124: You are the program manager for your project. You are workin...
Question 125: In your organization there are rules and procedures that the...
Question 126: A program manager learns that their company's organizational...
Question 127: Joan is the program manager for her organization. Throughout...
Question 128: A program manager recognizes that a successful resource bein...
Question 129: According to Standard for Program Management, Second Edition...
Question 130: A large international manufacturing company is centralizing ...
Question 131: You are the program manager of the NHQ Program for your orga...
Question 132: Identify the term described in the statement given below? "T...
Question 133: A program manager initiates a developmental program. Signifi...
Question 134: A new program manager joins a multi-year program that has be...
Question 135: Which of the following is described in the statement given b...
Question 136: There are five stages of team development. At which stage ar...
Question 137: A three-year program using vendor contracts, incorporating r...
Question 138: A program manager joins a team to fix a troubled enterprise-...
Question 139: Program manager B leaves the program and program manager A t...
Question 140: The program manager completed the program's benefits analysi...
Question 141: A program manager at a pharmaceutical company plans a new dr...
Question 142: Which of the following is not a template element that is des...
Question 143: You are the program manager for your organization. You have ...
Question 144: You are the program manager for your company and are monitor...
Question 145: In your program you must adhere to Six Sigma as part of your...
Question 146: Near the end of an ongoing project, the program manager is t...
Question 147: You are the program manager for your organization. You are p...
Question 148: Which project management meeting allows stakeholders to meet...
Question 149: In a program's definition phase, a program manager in countr...
Question 150: You are the program manager for your company and evaluating ...
Question 151: To create market advantage, a program sponsor requests accel...
Question 152: An experienced program manager is leading a development prog...
Question 153: A new program is being initiated for the HNQ Organization. T...
Question 154: Your program exists within a matrix structure. Your program ...
Question 155: A critical program for a company fails to delivers its inten...
Question 156: Which one of the following is not an output of the direct an...
Question 157: An organization must accelerate a product to market. The pro...
Question 158: Your program has a budget at completion of $1,550,000 and is...
Question 159: An ice cream company wants to introduce a new flavor to a ne...