Valid PgMP Dumps shared by ExamDiscuss.com for Helping Passing PgMP Exam! ExamDiscuss.com now offer the newest PgMP exam dumps, the ExamDiscuss.com PgMP exam questions have been updated and answers have been corrected get the newest ExamDiscuss.com PgMP dumps with Test Engine here:
The project managers for component projects A and B schedule the same resource to perform tasks during the same timeframe, resulting in an over-allocation. The program manager reviews the program resource management plan, determines that project A can wait until the resource becomes available, and assigns the resource to project B. This is an example of which of the following?