While preparing an earned value analysis (EVA) for the sponsor, the project manager provided this information in the latest project report: * Approved Work Package Cost Estimates: US$9,500 * Contingency reserves: $500 % * Management reserves: 10% of contingency reserves * Percent complete of the project: 50% * Planned percent of the project: 40% * Actual costs of the project: US$4,500 What is accurate about the project status?