<< Prev Question Next Question >>

Question 196/210

Drag the items on left side to the matching term within the correct project.

LEAVE A REPLY

Your email address will not be published. Required fields are marked *

Question List (210q)
Question 1: A project manager presented the project schedule to the mam ...
Question 2: A project manager is assigned to a project in a company that...
Question 3: Two weeks after the approval of the project management plan ...
Question 4: Due to delays on some activities one of the project team mem...
Question 5: After 1 year Into the life cycle of an ongoing residential p...
Question 6: A stakeholder is requesting that the project manager share p...
Question 7: A project manager accepts a delivery at the project site but...
Question 8: During a project planning meeting, the customer is not sure ...
Question 9: Important projects in the portfolio backlog need to be deliv...
Question 10: During the third iteration of a project, the main sponsor re...
Question 11: A project manager is meeting with the project sponsor regard...
Question 12: A project just kicked off and management's expectation is to...
Question 13: For an ongoing project, match the key performance indicators...
Question 14: A company is moving to a hybrid approach and conducted capac...
Question 15: The business manager and the product owner are requesting a ...
Question 16: A protect manager has just finished planning for a project w...
Question 17: From previous lessons learned working with a client, a proje...
Question 18: A project manager arranged a team-building activity to build...
Question 19: A project manager joins a team that is providing a customize...
Question 20: A project manager is m the middle of a project when one of t...
Question 21: The project sponsor of a major initiative is consistently ch...
Question 22: During a project status update by the project management off...
Question 23: A company has hired a vendor to deliver a scope of work and ...
Question 24: A project manager has been managing a project for several mo...
Question 25: A new project manager has been assigned to a project that is...
Question 26: A project manager is assigned to lead a newly formed agile t...
Question 27: A project manager is assigned to a technical research projec...
Question 28: In a construction project for a new building, the project ma...
Question 29: A project for a new product launch is in a very initial stag...
Question 30: Since the beginning of a project, the product owner keeps as...
Question 31: The product team is progressing with a prototyping approach ...
Question 32: During the retrospective ceremony, the agile team is talking...
Question 33: A team member shares with their functional manager some nega...
Question 34: The project management office (PMO) assigns a project manage...
1 commentQuestion 35: A project manager has team members around the world in many ...
Question 36: A project manager who Is new to an organization is given dat...
Question 37: During an inspection, the production phase was stopped becau...
Question 38: The project manager realizes that the product owner has a lo...
Question 39: A project manager has just finished initiating a project. Wh...
Question 40: A company wants to increase the commercial value of one of i...
Question 41: A project is behind schedule and over budget, resulting in a...
Question 42: A project manager Is working on the initial phases of a high...
Question 43: A project manager finished reviewing the project deliverable...
Question 44: A project manager is assigned to a new project. Many of the ...
Question 45: A project manager is managing a project which is approaching...
Question 46: A project manager has joined a company m an unfamiliar indus...
Question 47: As part of a temporary assignment, a project manager is lead...
Question 48: Early in the execution phase, a project manager discovers th...
Question 49: For an agile pilot project, the sponsor arranged an early pr...
Question 50: After a performance review, a team member approaches the pro...
Question 51: A technical manager newly appointed by the client, visits th...
Question 52: At the end of planning a new project, the project manager ne...
Question 53: A project manager has been assigned to a project and receive...
Question 54: A Scrum team has committed to delivering a specific capabili...
Question 55: During the course of a project the project manager's immedia...
Question 56: A project manager is managing multiple teams. One team membe...
Question 57: An agile project is starting its seventh out of eight iterat...
Question 58: Team members are having a discussion with the project manage...
Question 59: A project manager has been assigned to take over an existing...
Question 60: A research and development team is finishing up a two year i...
Question 61: A project manager learns from a marketing analyst that a com...
Question 62: The vendor for a new IT data center project failed to follow...
Question 63: A new relevant project stakeholder suggested a change to som...
Question 64: An agile team is working on a product deliverable in an orga...
Question 65: A senior business stakeholder with many years of experience ...
Question 66: The client will not agree to closure, claiming that the proj...
Question 67: An agile team is working on a project that will be launched ...
Question 68: After completion of a project with specific users in various...
Question 69: A project manager is executing a project where an external v...
Question 70: The project manager has initiated the project and the team's...
Question 71: An organization uses a predictive approach but is open to us...
Question 72: A project is being initiated, and almost every resource avai...
Question 73: A project manager for a strategic initiative realizes a new ...
Question 74: A project manager has been appointed to a multimillion-dolla...
Question 75: for a project has reported the potential for a delivery dela...
Question 76: During daily calls team members share task progress One team...
Question 77: A project manager is assigned to a hybrid project involving ...
Question 78: In a newly formed project team one experienced team member i...
Question 79: local company is developing a new product and. for the first...
Question 80: A project to develop a large hydropower plant is in the impl...
Question 81: In a hybrid project, the customer has issued a contract that...
Question 82: A project team was established for a community impacted by o...
Question 83: A key agile project team member takes a leave of absence in ...
Question 84: A project manager receives a request for proposal (RFP) from...
1 commentQuestion 85: A globally distributed project team is running behind schedu...
Question 86: During project execution, a project manager discovers that t...
Question 87: An agile team is making infrastructure changes to the human ...
Question 88: Development team members are located in three different time...
Question 89: A project manager scheduled a session to identify risks on t...
Question 90: A key stakeholder for a construction project has been spendi...
Question 91: A contractor delivering construction services to a company i...
Question 92: A research and development department is planning to develop...
Question 93: During a retrospective meeting a project manager hears that ...
Question 94: A project manager is using a hybrid approach for project del...
Question 95: A project manager and a stakeholder have different opinions ...
Question 96: A project manager was just assigned to a project as the lead...
Question 97: The project sponsor requested technical specifications for a...
Question 98: An agile project is 25% complete when the product owner chan...
1 commentQuestion 99: A project manager is leading a project in which key performa...
Question 100: The change control board (CCB) rejects a change request subm...
Question 101: A project team is having difficulties understanding technica...
Question 102: In an industrial plant, the owner has decided to add more ca...
Question 103: A project manager is tasked with managing a customer relatio...
Question 104: The project manager of a hybrid project learns that a stakeh...
Question 105: The project sponsor recently requested that a vendor begins ...
Question 106: A key stakeholder is upset because the final product deliver...
Question 107: During the design phase, a project manager realizes that the...
Question 108: A project manager is approaching the end of a project, and s...
Question 109: An agile project has just started, and the backlog is being ...
Question 110: A new team member is hired and the training is taking longer...
Question 111: In a project using a hybrid approach, the performance of the...
Question 112: A project manager is leading a project that is in an advance...
Question 113: A project manager is managing two agile teams and reviewing ...
Question 114: A project manager is leading a project which shows a trend t...
Question 115: A company has a lot of experience with predictive projects T...
Question 116: A project manager for a maintenance project has a contract t...
Question 117: An organization is producing a product using a hybrid approa...
Question 118: Drag the characteristics of the stage on the left to the cor...
Question 119: An agile project team is building a new product. The stakeho...
Question 120: During the implementation phase of a project, a new regulati...
Question 121: A project manager is leading a meeting with key stakeholders...
Question 122: Organizational downsizing has resulted in the key subject ma...
Question 123: During a retrospective review, many project team members say...
Question 124: A key project stakeholder who was a big supporter and motiva...
Question 125: A self-organizing team was delivering as committed. The team...
Question 126: A newly hired team member just joined the project team and r...
Question 127: During a regular review, the project manager of an agile pro...
Question 128: At the daily project meeting, team members are complaining a...
Question 129: A new facility project is being developed using a hybrid app...
Question 130: A company's project management office (PMO) has been trying ...
Question 131: A team is holding the first demonstration of the software bu...
Question 132: During project execution, a conflict occurs between the proj...
Question 133: A team is ready to start working on a project with a custome...
Question 134: A global company hired a project manager for a new implement...
Question 135: A junior team member escalates an issue to the project manag...
Question 136: The project manager is reviewing the program risks and issue...
Question 137: A company is initiating a project to decommission inefficien...
Question 138: A project manager is assigned to an important company projec...
Question 139: A few months into a project, several schedule issues have em...
Question 140: While managing a project, the project manager has just notic...
Question 141: A project manager has been assigned to lead a project to dep...
Question 142: The project manager started a new project and must ensure th...
Question 143: Due to a company merger and acquisition process, the main st...
Question 144: After a couple of iterations the project manager decides to ...
Question 145: A company that is heavily focused on delivering projects usi...
Question 146: A project team is experiencing delays in completing a task t...
Question 147: After a project team has been working on a project for sever...
Question 148: During the execution of a maintenance project the contractor...
Question 149: During the initiation stage of a multimedia exhibition-desig...
Question 150: While preparing an earned value analysis (EVA) for the spons...
Question 151: After the second iteration of a component development projec...
Question 152: Which three of the following scenarios are impediments to wh...
Question 153: In a functional organization, a product analyst is assigned ...
Question 154: A company is using a predictive approach for the development...
Question 155: A company's leadership team has decided to invest in a new p...
Question 156: As part of the strategic plan, a company decides to implemen...
Question 157: During initiation of a new product improvement project, a pr...
Question 158: An organization in a regulated industry has decided to switc...
Question 159: A project manager is leading an agile project in an organiza...
Question 160: A project manager created a contingency plan associated with...
Question 161: A project is being executed The project's life cycle is defi...
Question 162: A project manager is assigned to a project that is in develo...
Question 163: A team has different ideas on how to address a feature of a ...
Question 164: A team has been working together for several months and has ...
Question 165: A company has been following a predictive approach and alway...
Question 166: The project manager of an agile project has been asked to re...
Question 167: A project manager is leading a software development project....
Question 168: The project manager is experiencing delays with two critical...
Question 169: During an ongoing project a key resource asks the project ma...
Question 170: A stakeholder on a project has a reputation for being easily...
Question 171: During the implementation phase of a construction project th...
Question 172: Drag the interpersonal skill on the left to the correct scen...
Question 173: A company has decided to implement a new archiving system A ...
Question 174: An agile team member received certification on a new tool: h...
Question 175: During the last sprint review, the mam stakeholder complaine...
Question 176: A project learn member identified a defect in the initial so...
Question 177: A project manager has been asked to lead a project. The perf...
Question 178: At a meeting to receive approval for the project management ...
Question 179: A project is in the knowledge transfer phase, and a few subj...
Question 180: The project sponsor on an agile project informed the project...
Question 181: A company was awarded a project in a dangerous location that...
Question 182: A project manager has been moved to a new division and is in...
Question 183: In a multinational multi location project with virtual teams...
Question 184: An agile senior project team member suddenly resigns from th...
Question 185: A project manager has noticed that the performance of a new ...
Question 186: The product owner decides to launch a product after a couple...
Question 187: A high-performing team member's performance has been consist...
Question 188: During the execution of a project the project manager notice...
Question 189: A newly formed team has become accustomed to agile practices...
Question 190: A project manager is leading a project with several stakehol...
Question 191: During project execution, the project manager notices that t...
Question 192: An organization is transitioning to an agile environment. Th...
Question 193: Five agile teams working together on a product recently perf...
Question 194: A project manager is preparing a project closure report. The...
Question 195: A large corporation is transforming itself from a predictive...
Question 196: Drag the items on left side to the matching term within the ...
Question 197: A project manager for a large project's agile team is develo...
Question 198: A project manager notices that the team lacks a subject matt...
Question 199: A new project manager is assigned to a project midway throug...
Question 200: A project manager has just been assigned to a team that is d...
Question 201: While developing a new product, a key stakeholder expresses ...
Question 202: A project started 12 months ago and is currently on iteratio...
Question 203: Due to a recent budget reduction, two team members were rele...
Question 204: A company just started managing a project using an agile app...
Question 205: A project manager is managing a megaproject. The project sta...
Question 206: During a scope validation exercise toward the end of a proje...
Question 207: A new project manager is planning an information security pr...
Question 208: the project manager for some direction and advice on risk mi...
Question 209: During the course of a project, the project manager wants to...
Question 210: A project manager realizes that a project is becoming delaye...