Question 109/299

A project is three weeks behind schedule and the baseline finish date is two months away. The management team states there is no budget overtime pay.
What Should the project manager do to complete the propel on schedule?

Recent Comments (The most recent comments are at the top.)

Dr Pratul Sharma - Sep 02, 2020

This answer is wrong, correct answer is A, i.e. fast track the schedule because fast track does not add more cost...while crashing will add more cost...

LEAVE A REPLY

Your email address will not be published. Required fields are marked *

Question List (299q)
Question 1: A project manager shares project performance through status ...
Question 2: A project manager is working on the final report for a large...
Question 3: An organization is implementing changes to its financial ris...
Question 4: A project has closed, and the project manager moves on to a ...
Question 5: While preparing a project charter for a new project, a proje...
Question 6: You are a project manager for a software development project...
Question 7: A key deliverable requires a specific set of skills and know...
Question 8: A project manager is helping to draft a project because of t...
Question 9: The concrete for a project arrives on time, but the project ...
Question 10: A project has been in execution for three months. A new team...
Question 11: From prior experience with an organization, a project manage...
Question 12: You are a project manager, and you want to perform some anal...
Question 13: In your project, one of your project team leaves the site ea...
Question 14: The project manager of a technical team receives a complaint...
Question 15: While working on a project, the project team realizes that r...
Question 16: Upon approval, a new project manager immediately begins a pr...
Question 17: A company implements a project to design a new product for i...
Question 18: You are the project manager, managing a project to design a ...
Question 19: Outing a weekly review session a key stakeholder rejects a d...
Question 20: What is the contract type that transfers all risks to the se...
Question 21: An organization is awarded a large construction project. The...
Question 22: A data center facility was built near a resident community. ...
Question 23: A project manager working in a multinational organization no...
Question 24: An issue will cause the project team to miss a critical mile...
Question 25: A project manager is gathering formal project requirements A...
Question 26: You are a project manager working on gathering requirements ...
Question 27: A set of high-impact repetitive tasks must be executed durin...
Question 28: During project planning, the project manager wants to transf...
Question 29: A vendor who supplied material that failed to meet a technic...
Question 30: A project is in the closure phase. The deliverables have bee...
Question 31: A project manager is assigned to a project that is in progre...
Question 32: What should the team consider to be most important while cre...
Question 33: A project manager is working on a project for which some req...
Question 34: Which of the following is a tool and technique of the Identi...
Question 35: After a risk review, the project manager notes an increase i...
Question 36: A project team is developing a new enterprise resource plann...
Question 37: The client is pushing the development team for an urgent sof...
Question 38: A company has recurring quality issues with one of its sole-...
Question 39: In a project with a multigenerational team, some resources a...
Question 40: A concept that is unique to each organization and includes t...
Question 41: Which processes are in the Initiating process group?...
Question 42: Stakeholders determine that the business case considers 3D l...
Question 43: Six months into a project the first project milestone is due...
Question 44: Based on your success on previous projects, you have been as...
Question 45: You are managing an advertising software project in an agile...
Question 46: A project manager wants to create the risk register. What sh...
Question 47: While reviewing a status report, a project manager notices t...
Question 48: Midway through implementation of a construction project, a s...
Question 49: A project manager is leading a team with members from many d...
Question 50: You are managing a highly complex drug manufacturing project...
Question 51: You are a project manager for a software project. Various to...
Question 52: Which of the following tools and techniques is most likely u...
Question 53: A customer asks the project manager to estimate the time req...
Question 54: When conducting procurements, what process should the projec...
Question 55: You have just joined a new organization as a project manager...
Question 56: You are working on a warehouse project when you realize that...
Question 57: Who is the Key Person in the kick-off meeting?...
Question 58: A financier is considering investing money on a future luxur...
Question 59: A project manager is working on a building construction proj...
Question 60: The charter for a project to build a new financial reward sy...
Question 61: A demanding project stakeholder insists that an additional f...
Question 62: ZULFI is the Project Manager of a new product development pr...
Question 63: A recently promoted project manager must facilitate the week...
Question 64: A project manager receives an approved request related to a ...
Question 65: A project manager plans the agenda tor a kick-off meeting. A...
Question 66: While developing a project's benefits management plan, a pro...
Question 67: You are a project manager working on a software development ...
Question 68: An external audit concludes that a project is six to 12 mont...
Question 69: You are managing a software development project. You divided...
Question 70: While developing the cost management plan, the project manag...
Question 71: An independent, third-party auditor conducted scope verifica...
Question 72: To estimate the cost of project activities for a new project...
Question 73: Due to recent organizational changes, a number of project st...
Question 74: When writing the roles and responsibilities of your team mem...
Question 75: After a steering committee meeting, it is decided that the p...
Question 76: You are performing the Perform Qualitative Risk Analysis pro...
Question 77: During a project review meeting, the project manager observe...
Question 78: A project manager is leading a new project that involves cro...
Question 79: A customer asks the project manager to deliver a project in ...
Question 80: If an agile approach is used, which of the following techniq...
Question 81: A company wants to start a new project to build an innovativ...
Question 82: A project's original budget at completion (BAC) was calculat...
Question 83: Your project has 15% probability of having a profit of $10,0...
Question 84: During a project steering committee meeting, the project man...
Question 85: The project manager has calculated the schedule performance ...
Question 86: Alter the root cause of defective deliverables is identified...
Question 87: A project manager is assigned to a project in its execution ...
Question 88: A project's deliverables due is approaching, but one team me...
Question 89: The project manager completed the release planning and is mi...
Question 90: A stakeholder frequently requests new functionalities to be ...
Question 91: A project manager has been assigned to a new project. During...
Question 92: The project manager of a large software implementation proje...
Question 93: A project manager invites the new CIO to a meeting to review...
Question 94: During a protect status meeting, the project manager identif...
Question 95: Two team members argue about who will perform and report the...
Question 96: A client informs the project manager that a team member is u...
Question 97: Two learn members have continuing conflicts that affect team...
Question 98: The project manager for a new project wants to discuss proje...
Question 99: A company is using Lean Six Sigma methodology on a project. ...
Question 100: A project learn is evaluating whether promotional activities...
Question 101: During the execution of a project, the project manager finds...
Question 102: A project manager is creating a program evaluation and revie...
Question 103: A local supplier is unable to meet a delivery date. The proj...
Question 104: You are managing a large project team that was joined by new...
Question 105: During a project review, the construction manager reports th...
Question 106: You project is running with a CPI of 1.1. The EAC is $100,00...
Question 107: After receiving the hardware components from a vendor that w...
Question 108: During a project review meeting, a team member disagrees wit...
1 commentQuestion 109: A project is three weeks behind schedule and the baseline fi...
Question 110: A project manager for a 12-month project has a budget of US$...
Question 111: During the construction of a port, a nearby fishing communit...
Question 112: During a project's execution phase, a new stakeholder is ide...
Question 113: A low-priority and low-risk change request has been planned ...
Question 114: A project manager reviews the risk register and is concerned...
Question 115: A project to create a new product is completed and introduce...
Question 116: As a project manager, you are ensuring that the quality mana...
Question 117: A Strike at a contracted production plant affects the delive...
Question 118: A project manager is having difficulty obtaining resources f...
Question 119: The CPI= 0.7 and the SPI=1.2. How is your project doing?...
Question 120: After conducting a data analysis, a project manager determin...
Question 121: A meeting to present, discuss, and approve the project manag...
Question 122: After reviewing an approved project's resource management pl...
Question 123: During a crisis, additional resources and time were required...
Question 124: A team member comes to the project manager and explains that...
Question 125: During project implementation, the project manager reviews i...
Question 126: A probability and impact matrix is useful for:...
Question 127: A project manager notices an unusually high rate of risks, b...
Question 128: A senior engineer notifies the project manager that there wi...
Question 129: You are a Project Manager working on a project to create hig...
Question 130: After receiving the approved project charter, a stakeholder ...
Question 131: A project is in the execution phase and product testing is a...
Question 132: After several weeks on a new project, the project manager le...
Question 133: A project plans the agenda for a kick-off meeting. As one of...
Question 134: The project manager is given two teams that are restricted t...
Question 135: A project manager in a Cross-functional organization needs t...
Question 136: An approved change request adds an incentive to a lump sum c...
Question 137: You are a project manager and you are in the closing phase. ...
Question 138: An IT project is approved and a project management plan is i...
Question 139: A new change has been requested for a project two weeks befo...
Question 140: Midway through a project, a project manager determined the p...
Question 141: A protects outcome is highly sensitive to and dependent upon...
Question 142: What tool should the project manager use to demonstrate to t...
Question 143: During your project meeting, a problem was discussed with on...
Question 144: A project manager has a team of diverse professionals with d...
Question 145: Two years back, your organization awarded a fixed price cont...
Question 146: A new execute asks the project manager to share sensitive pr...
Question 147: A project manager is initiating a highly controversial proje...
Question 148: A project team member indicates that a change must be made t...
Question 149: Due to a lack of experience, a team is unable to commit to m...
Question 150: A stakeholder refuses to accept delivery of a project that h...
Question 151: To reduce an product's defect ratio, a corrective action is ...
Question 152: The process that translates the quality management plan into...
Question 153: Your project is due for a financial review and you have gath...
Question 154: Since the client was on leave, a project manager handed over...
Question 155: A project manage identifies the root cause of a quality issu...
Question 156: Due to a recent incident, a dissatisfied stakeholder files a...
Question 157: A project to deliver financial and administrative changes re...
Question 158: A project manager's team has been expanding in more geograph...
Question 159: A project team member encounters an issue and identifies a w...
Question 160: A project's cost performance index (CPI) is 0.3. The CFO ins...
Question 161: Just prior to a project's execution phase, a project manager...
Question 162: During a stakeholder meeting, the project manager receives r...
Question 163: A project status report shows that the earned value (EV) is ...
Question 164: A project manager learns that the government plans to introd...
Question 165: A senior quality manager complains about a new drone develop...
Question 166: What should the project manager use to compare different sup...
Question 167: To begin transitioning the final deliverables to the client,...
Question 168: A project manager just arrived in a new company department a...
Question 169: During protect execution the project manager notices that th...
Question 170: During a project demonstration, a team member provides sampl...
Question 171: You are a Project Manager, and you want your team to use (WB...
Question 172: A project manager is unable to explain why several Scrum tea...
Question 173: If a project has a 40 percent chance of a $10,000 profit and...
Question 174: A key project team member takes a leave of absence with an u...
Question 175: A vendor provides notices of a delay in the delivery of a ke...
Question 176: schedule overruns A project manager is just finishing up a p...
Question 177: The project manager of a pipeline project hires a constructi...
Question 178: During project execution, the marketing manager stales that ...
Question 179: A protect manager has just completed a stakeholder engagemen...
Question 180: As a project manager for a construction project, you underst...
Question 181: An issue arises on a project A team member recalls that this...
Question 182: A company has a history of implementing system integration p...
Question 183: A recent project took 12 months to complete: however' a new ...
Question 184: During project execution, a project team develops a new resp...
Question 185: As part of a project, a new plant is being constructed in a ...
Question 186: A start-up company's project team completes its first produc...
Question 187: A proved is delivered that meets the approved business requi...
Question 188: A multinational company is locally developing a digital prod...
Question 189: A sponsor proposes a project scope change that is popular wi...
Question 190: After preparation of the project management plan, the projec...
Question 191: To increase sates, a marketing team wants to introduce a new...
Question 192: Mark is a project manager working on a compliance project in...
Question 193: During testing of a project component a senior tester discov...
Question 194: During a project update meeting, one of the key stakeholders...
Question 195: A prevents action is approved by the change control board (C...
Question 196: Which of the following can the project manager use to group ...
Question 197: After performing a risk analysis, the project manager realiz...
Question 198: A stakeholder with a high degree of impact now requires more...
Question 199: An audit was conducted on a project during close out The iss...
Question 200: A project manager conducts weekly, face-to-face meetings wit...
Question 201: The project manager discovers that the vendor did not perfor...
Question 202: The Conduct Procurements process receives bids or proposals ...
Question 203: Team members on a life cycle replacement project are accusto...
Question 204: The product owner notifies the project manager about a risk ...
Question 205: A key project stakeholder requests that the project manageme...
Question 206: An organization is kick-starting a project in an emerging ma...
Question 207: You are a project manager working on a software development ...
Question 208: A project manager realizes that a new government regulation ...
Question 209: You are managing a construction project. You have included t...
Question 210: Faulty vendor supplied parts must be returned and reordered,...
Question 211: A medium-sized protect has a high-level timeline at project ...
Question 212: A software company is asked to build an application based on...
Question 213: A project manager assumes a multi-country project that is ex...
Question 214: A project successfully met its goals on time and all deliver...
Question 215: You are managing a software development project using an agi...
Question 216: During a progress review of a project near completion, there...
Question 217: A contract project manager has been employed to work on a la...
Question 218: The success of an infrastructure project depends upon the ar...
Question 219: A project manager needs to obtain a new resource for a proje...
Question 220: During the kick-off meeting for a warehouse expansion, the p...
Question 221: Because critical distribution needs were not identified and ...
Question 222: To ease the workload on the acceptance testing team a key st...
Question 223: A multinational company with a cross-border project wants to...
Question 224: Midway through the design phase of a software development pr...
Question 225: A product implementation project has a baseline schedule tha...
Question 226: As an automation project nears completion, the engineering t...
Question 227: During the execution of a project, the project manager ident...
Question 228: The project charter for a new project is authorized, and the...
Question 229: Midway through project implementation, stakeholders lose con...
Question 230: A project manager for a US$15 million construction project m...
Question 231: A project manager is using control charts to determine wheth...
Question 232: Although previously identified project risks have not yet ma...
Question 233: Which of the following are tools and techniques of the Monit...
Question 234: A vendor submits a high-level project schedule for a three-y...
Question 235: Significant customer change requests to project scope result...
Question 236: The project charter for a new urgent project was recently si...
Question 237: All of the following are inputs to the develop Project Chart...
Question 238: After completing the project charter, the project manager se...
Question 239: Which processtool is conflict management?...
Question 240: A project manager receives a request for proposal (RFP) and ...
Question 241: A project manager completes a protect management plan for a ...
Question 242: A new payment system is being built using agile principles. ...
Question 243: You are managing a project in the manufacturing industry. Yo...
Question 244: Which of the following is a tool to assess the current and d...
Question 245: This process is concerned with determining the engagement le...
Question 246: A project meets time and cost targets, and the project spons...
Question 247: During a project's execution phase, project members have fre...
Question 248: A protect manager leaves the company and a new project manag...
Question 249: A project team delivers a system in its pilot phase, and the...
Question 250: You are the Project Manager and are currently in the monitor...
Question 251: A project manager joins an existing project. On their first ...
Question 252: You are managing a critical project with virtual teams locat...
Question 253: During the last few days of an open request for proposal (RF...
Question 254: A project is delivered that meets the approved business requ...
Question 255: While reviewing project documentation, a project manager dis...
Question 256: A project manager discover that material costs have increase...
Question 257: While preparing for project hand-over to the operations team...
Question 258: Which of the following is NOT an input of the close projecto...
Question 259: A project has been stopped during the execution phase becaus...
Question 260: You are a project manager working on a software development ...
Question 261: The project sponsor indicates to the project manager that du...
Question 262: A project team member identifies a quality issue that may ca...
Question 263: One of the stakeholders on the project led a change request ...
Question 264: A company has decided to use agile methodology for the first...
Question 265: A company has started a drainage improvement project to avoi...
Question 266: A software business partner of a project is delayed in the d...
Question 267: A project is nearing completion when the project manager lea...
Question 268: Project risks have been identified through a brainstorming s...
Question 269: A project manager notices that work started by the project t...
Question 270: The sponsor of your project is particularly interested in re...
Question 271: The project charter initiates the project and provides high-...
Question 272: A project is being audited to ensure compliance with organiz...
Question 273: A project manager needs to add a subject matter expert (SME)...
Question 274: Willie reviewing project performance, the project manager no...
Question 275: An ongoing cross-functional project has team members located...
Question 276: Company A hires a new project manager to join an existing pr...
Question 277: A division manager wants to transfer a key team member off o...
Question 278: International Management Company recently terminated a consu...
Question 279: What should the project manager use to prepare this?...
Question 280: A project must be simultaneously implemented in two countrie...
Question 281: You are managing a complex software development project for ...
Question 282: A company is implementing a new IT tool but the project is b...
Question 283: A project's core team was reassigned to a partially complete...
Question 284: In your project, if earned value (EV) is larger than planned...
Question 285: Government regulations require that project deliverables be ...
Question 286: Upon completion of testing, the client requests changes beca...
Question 287: A development project's earned value is US$640,000. and the ...
Question 288: A project manager is working on a technical project with a t...
Question 289: After a major milestone release, one of the key stakeholders...
Question 290: During a project, some products are acquired. The buyer and ...
Question 291: You are a project manager working on a software development ...
Question 292: Six weeks after the addition of new project resources, the p...
Question 293: During the creation of the project schedule, the project man...
Question 294: During the deployment of a new system, an unexpected power o...
Question 295: In which phase the Kick off Meeting established?...
Question 296: You are participating in the development of the project char...
Question 297: A project manager is working in a hybrid environment using b...
Question 298: A project manager receives an email requesting modification ...
Question 299: Delays from two software vendors are causing testing times t...