What is the difference between the internal goals and the external goals of the PMO?
Correct Answer: A
The distinction betweeninternalandexternal goalsof the PMO lies in who sets and agrees on them: * Internal goalsare established within the PMO team and are related to internal performance, processes, and team-based metrics. They focus on optimizing internal operations and improving efficiency. * External goals, on the other hand, are agreed upon withPMO stakeholders. These goals focus on delivering value to external parties, ensuring that the PMO meets the expectations of stakeholders such as upper management, clients, and external partners. This alignment of internal and external goals is critical for ensuring that the PMO adds value both internally and externally, maintaining a balanced approach to performance.