Valid PMI-RMP Dumps shared by EduDump.com for Helping Passing PMI-RMP Exam! EduDump.com now offer the newest PMI-RMP exam dumps, the EduDump.com PMI-RMP exam questions have been updated and answers have been corrected get the newest EduDump.com PMI-RMP dumps with Test Engine here:
A risk manager is conducting a qualitative risk analysis for a renewable energy project that faces tight deadlines. The team identifies risks such as weather unpredictability, material cost fluctuations, and potential regulatory delays. While some members advocate prioritizing high-likelihood risks, others emphasize addressing unlikely but high-impact risks. What should the risk manager do?
Correct Answer: C
Qualitative risk analysis requires consideration of both the likelihood and the impact of each risk to properly prioritize them, rather than focusing only on probability or only on impact. The PMBOK Guide states: "During qualitative risk analysis, risks are prioritized for further analysis or action by assessing and combining their probability of occurrence and impact on project objectives." - PMBOK Guide, 6th Edition, Section 11.3 Therefore, the risk manager should evaluate all identified risks, considering both likelihood and impact. References: PMBOK Guide, 6th Edition, Section 11.3 Practice Standard for Project Risk Management, PMI, Section 5.4