A project team is concerned about a risk which, if occurs, might add additional complexity to their work. The team will need help from an external vendor, but the contracting process is long. What should the risk manager do in this case?
Correct Answer: A
If a risk requires external help and the contracting process is long, it is prudent to start the process immediately to avoid delays. This proactive approach ensures that the necessary resources will be available when needed. According to PMI guidelines, early action to address risk is essential, especially when external dependencies are involved. Documenting the risk in the risk register or analyzing it further can be done concurrently, but starting the contracting process mitigates the risk of delay.