<< Prev Question Next Question >>

Question 72/89

The project team recorded a risk in the risk register indicating that weather-related delays may impact equipment delivery during project execution. When it is time to request the equipment shipment there is bad weather, but the client wants the equipment delivered anyway.
What should the project manager do?

LEAVE A REPLY

Your email address will not be published. Required fields are marked *

Question List (89q)
Question 1: The project manager and the risk manager of a new project to...
Question 2: While executing an oil extraction project in an environmenta...
Question 3: A mega facility development project is evaluating some optio...
Question 4: During the project's lifecycle, project risk managers must m...
Question 5: In reviewing the team's identified project risks, a project ...
Question 6: An experienced and the only developer on a software implemen...
Question 7: A project's design has been completed and approved on time. ...
Question 8: The project risk manager for an environmental preservation p...
Question 9: A risk manager completed risk response planning for a projec...
Question 10: A project manager for a large product development project as...
Question 11: While developing a risk management plan for a complex progra...
Question 12: A company manages confidential customer information, and a d...
Question 13: Project stakeholders can often be risk averse with little to...
Question 14: During project execution, a project manager invites the stak...
Question 15: A project lihat was in the execution phase for the last six ...
Question 16: The project manager has completed four projects all with sim...
Question 17: A risk manager is managing risks of a mission critical appli...
Question 18: After starting a new pipeline project, a risk manager schedu...
Question 19: A project team identifies that there is a probability of mis...
Question 20: The risk manager is facilitating risk planning activities wi...
Question 21: A project team working on a large software deployment projec...
Question 22: The project manager wants to use an objective method to eval...
Question 23: The risk manager conducted an updated Monte Carlo simul-atio...
Question 24: A project team identified some risks in a project. Team memb...
Question 25: The project manager performed' a variance analysis on the pr...
Question 26: A risk manager notices that a risk owner is facing challenge...
Question 27: A project manager is educating the project team on risk mana...
Question 28: What is an example of legal and regulatory requirements and/...
Question 29: A project team is concerned about a risk which, if occurs, m...
Question 30: A project team has just completed a project plan, which incl...
Question 31: A risk manager for a large project has completed documenting...
Question 32: A project manager wants to work on understanding the project...
Question 33: During project development, a risk manager notices that a ma...
Question 34: The project director and project manager have met with the b...
Question 35: After the initial assessment of a new project, a project man...
Question 36: When conducting a risk identification exercise, what two act...
Question 37: The project manager for project X was expecting the mobiliza...
Question 38: A project manager is working on a construction project. Base...
Question 39: During project planning, a risk is identified for which the ...
Question 40: The project manager is reviewing the lessons learned from a ...
Question 41: The risk manager of a major project needs to ensure the orga...
Question 42: During the monthly executive review meeting, the project spo...
Question 43: A certain risk is identified for a major project, and the ri...
Question 44: During the construction of a housing development, a project ...
Question 45: Some issues and unexpected results were found after completi...
Question 46: Three months into a program, multiple workstreams are showin...
Question 47: A risk manager is reviewing documentation for a project foll...
Question 48: A project manager is trying to realize benefits from new mat...
Question 49: In a project to promote public health and mitigate health ri...
Question 50: A key project is delayed and all contingency reserves have b...
Question 51: In a large enablement project with strict time lines, risks ...
Question 52: When approving the risk contingency budget for a project, th...
Question 53: Which statement describes the risk portrayed on the risk mat...
Question 54: A risk manager reviews a Monte Carlo schedule risk analysis ...
Question 55: A risk manager and relevant stakeholders have completed a ri...
Question 56: During a meeting to develop the risk management plan, the ri...
Question 57: A company is preparing a formal response to bid for an infra...
Question 58: A risk manager is facilitating a risk identification worksho...
Question 59: Towards the end of definitive design, project costs have inc...
Question 60: Business rhythm can fluctuate greatly between different indu...
Question 61: Some project risks are applicable for the project's lifecycl...
Question 62: Stakeholder holiday schedules and availability of raw materi...
Question 63: A project manager has been assigned to a project that is jus...
Question 64: In a large industrial business, an on-going system developme...
Question 65: . A project manager is identifying risks on a project and de...
Question 66: There is confusion among risk action owners on a project abo...
Question 67: A project manager realizes the team undertaking the project ...
Question 68: A risk management professional is in the process of categori...
Question 69: A risk manager administered a pre-workshop risk survey in pr...
Question 70: A risk manager is assigned to a new system deployment projec...
Question 71: A project manager has determined that they cannot outsource ...
Question 72: The project team recorded a risk in the risk register indica...
Question 73: At an oil and gas company, a major unified management inform...
Question 74: A risk manager wants to determine what risk has the biggest ...
Question 75: A risk manager and project team are managing a software syst...
Question 76: A project team in a multinational organization is working on...
Question 77: A risk manager recently had to take an unexpected leave of a...
Question 78: An external vendor needs to be contracted to provide additio...
Question 79: An organization that spans across different countries underg...
Question 80: A supplier Is delayed in delivering fuel for a project. The ...
Question 81: Product testing can be done in multiple ways. A few project ...
Question 82: The risk manager loaded the risk register, built the risks i...
Question 83: The project team has correctly identified, assessed, and pla...
Question 84: A risk manager manages risks in a construction project. A st...
Question 85: Multiple new risks have come up on a project that were not i...
Question 86: The project manager reviews project risks with the risk mana...
Question 87: A project manager has just been assigned to a new project. T...
Question 88: A large, land-based infrastructure project has begun. The pr...
Question 89: An organization faces immense competition in the market and ...