Valid PMI-RMP Dumps shared by EduDump.com for Helping Passing PMI-RMP Exam! EduDump.com now offer the newest PMI-RMP exam dumps, the EduDump.com PMI-RMP exam questions have been updated and answers have been corrected get the newest EduDump.com PMI-RMP dumps with Test Engine here:
Multiple new risks have come up on a project that were not included on the risk register. The project manager met with the team to explain that risk management is critical for the success of the project, and risk identification is key. What should the project manager do next?
Correct Answer: D
The project manager should apply an iterative approach to risk identification, which involves continuous risk identification throughout the project lifecycle. This will help to identify and address new risks that may arise during the project. According to the PMBOKGuide, risk identification is the process of determining which risks may affect the project and documenting their characteristics. It is an iterative process because new risks may evolve or become known only as the project progresses through its life cycle. There are many techniques available for risk identification and assessment, such as brainstorming, interviews, checklists, SWOT analysis, cause and effect diagrams, etc. The project manager should apply an iterative approach to risk identification to ensure that all relevant risks are captured and updated throughout the project. The project manager should also involve the project team and other stakeholders in the risk identification process to obtain their input and perspectives. The other options are not valid for the next step after explaining the importance of risk management to the team: Review assumptions and constraints around risks: This is a technique for risk identification, but it is not the only one. The project manager should use a combination of techniques to identify risks, not just focus on one aspect. Also, reviewing assumptions and constraints is not the same as applying an iterative approach, which implies repeating the risk identification process at regular intervals or when changes occur. Develop the risk response plans for identified risks: This is a step in the Plan Risk Responses process, which comes after the Perform Qualitative Risk Analysis and Perform Quantitative Risk Analysis processes. The project manager should not develop the risk response plans before identifying and analyzing the risks. Determine the likelihood and impact of the risks: This is a step in the Perform Qualitative Risk Analysis process, which comes after the Identify Risks process. The project manager should not determine the likelihood and impact of the risks before identifying them.