One way to make it more likely practice project risk management on projects is to______________
Correct Answer: A
Meetings are a tool and technique in the control risks process. Risk management should be an agenda item at periodic status meetings. While the amount of time needed for risk management will vary depending on the identified risks, their priority, and the difficulty of the response, the more often risk management is practiced, the easier it becomes. Frequent discussions about risk make it more likely that risks and opportunities will be identified. [Monitoring and Controlling] PMI®, PMBOK® Guide, 2013, 352