<< Prev Question Next Question >>

Question 83/190

A newly assigned project manager is reviewing the project documents with stakeholders to identify opportunities that will fast track the project and realize the financial benefits of early completion. What document should be updated at the end of the review?

LEAVE A REPLY

Your email address will not be published. Required fields are marked *

Question List (190q)
Question 1: Ben is the project manager of the YHT Project for his compan...
Question 2: A high-profile, high-priority project within your organizati...
Question 3: Wendy is the project manager of the FBL project for your com...
Question 4: Many companies self insure against some risk. Problems which...
Question 5: Gary is the project manager of the MMQ project for his compa...
Question 6: What project management plan is most likely to direct the qu...
Question 7: During qualitative risk analysis you want to define the risk...
Question 8: Joan is a project management consultant and she has been hir...
Question 9: Fill in the blank with an appropriate phrase. The _________ ...
Question 10: Which of the following techniques examines the degree to whi...
Question 11: Mark works as a project manager of the NNH project. In this ...
Question 12: Tom works as a project manager for BlueWell Inc. He is deter...
Question 13: You are the project manager for your company and a new chang...
Question 14: Which of the following characteristics would a risk-tolerant...
Question 15: You are the project manager of the BlueStar project in your ...
Question 16: During what process should a project manager assign a risk o...
Question 17: Which of the following is the primary project artifact used ...
Question 18: What is the primary difference between a risk audit and a ri...
Question 19: You are the project manager for your organization. You have ...
Question 20: Don has hired Jerry, a contractor, to complete a portion of ...
Question 21: Tracy is the project manager of the NLT Project for her comp...
Question 22: Adrian is a project manager for a new project using a techno...
Question 23: Gary is the project manager for his project. He and the proj...
Question 24: When does the Identify Risks process take place in a project...
Question 25: Which of the following risk responses delineates that the pr...
Question 26: Ned is the project manager of the HNN project for your compa...
Question 27: The risk register contains which of the following?...
Question 28: One way to make it more likely practice project risk managem...
Question 29: Which of the following processes involves choosing the alter...
Question 30: Linda is the project manager of the NAB Project. One of the ...
Question 31: The project manager must evaluate two separate contractors f...
Question 32: Which positive risk response best describes a teaming agreem...
Question 33: You are the project manager of the AFD project for your comp...
Question 34: In the country where a project is being executed, customs pr...
Question 35: What are common examples used to communicate risk probabilit...
Question 36: Work performance information in control risks means that____...
Question 37: Which analysis method has a lower standard deviation?...
Question 38: You are the program manager for your organization. Managemen...
Question 39: ____ analysis is a statistical concept that calculates the a...
Question 40: The risk register is developed during the initial phases of ...
Question 41: The Project Risk Management knowledge area focuses on which ...
Question 42: Fred is the project manager of the CPS project. He is workin...
Question 43: You work as a project manager for BlueWell Inc. Management h...
Question 44: Because risk management is relatively new on projects in you...
Question 45: You are the project manager of the HQQ Project for your comp...
Question 46: The team has just completed a risk response planning session...
Question 47: You are the project manager for your organization. You are w...
Question 48: A risk manager is conducting a risk audit review at project ...
Question 49: You and your project team are identifying the risks that may...
Question 50: Which of the following is a key element of neuro-linguistic ...
Question 51: A company is executing a high-visibility project to develop ...
Question 52: A race director is planning a marathon with US$80,000 in upf...
Question 53: Mary is the project manager for the BLB project. She has ins...
Question 54: You are the project manager of the NHJ project for your comp...
Question 55: A project in the execution phase at the customer's site has ...
Question 56: There are four inputs to the Monitoring and Controlling Proj...
Question 57: You are the project manager of the NHH project for your comp...
Question 58: There are seven risks responses that a project manager can c...
Question 59: Joyce is the project manager for her company. Joyce and her ...
Question 60: A well established project begins to experience cost overrun...
Question 61: You are the project manager of the HJK project for your orga...
Question 62: You are the project manager of the HJU project for your comp...
Question 63: Which of the following is an effective channel for risk miti...
Question 64: Yolanda is the project manager of a high-profile project for...
Question 65: Henry is the project manager of the QBG Project for his comp...
Question 66: Your project uses a piece of equipment that if the temperatu...
Question 67: You are interviewing members of a project team to test their...
Question 68: You are the project manager for Genpact Inc. You have establ...
Question 69: Rex is the project manager of the BDF Project. This project ...
Question 70: You work as a project manager for BlueWell Inc. You are invo...
Question 71: You are the project manager of the GGH Project in your compa...
Question 72: What would be the next step after determining the agreed-upo...
Question 73: You are the project manager of the GHY project for your comp...
Question 74: You work as a project manager for BlueWell Inc. Your project...
Question 75: Tom is the project manager for his organization. In his proj...
Question 76: Tom is the project manager of the GGG project for his compan...
Question 77: Beth is the project manager of the BFG Project for her compa...
Question 78: You work as a project manager for BlueWell Inc. You are perf...
Question 79: At the time the risk register is first prepared, it should c...
Question 80: Wendy is the project manager of the NNJ project for her comp...
Question 81: During which of the following processes, probability and imp...
Question 82: Which of the following is NOT an objective of a risk audit?...
Question 83: A newly assigned project manager is reviewing the project do...
Question 84: You are the project manager for a new website for the local ...
Question 85: As a result of the Control Risk process, the project manager...
Question 86: You are the project manager for a construction project. The ...
Question 87: Two companies merge. The executive leadership team for the n...
Question 88: You are the project manager of the KJH Project and are worki...
Question 89: Jeff, a key stakeholder in your project, wants to know how t...
Question 90: You are the project manager of the NNH project. In this proj...
Question 91: What is the purpose of mitigating negative risks as a part o...
Question 92: Rachel is the project manager of the KJH Project for her com...
Question 93: You work as a project manager for BlueWell Inc. Your project...
Question 94: A regional vendor for custom manufactured steel oil derricks...
Question 95: You are the project manager of a large construction project....
Question 96: Harold is the project manager of a large project in his orga...
Question 97: You are the project manager of the NHQ project for your comp...
Question 98: You are the project manager of the NHK Project. Management w...
Question 99: You are the project manager of the NKQ project for your orga...
Question 100: You work as a project manager for BlueWell Inc. You are work...
Question 101: During project execution, the project team realizes that the...
Question 102: A common understanding of the value of risk management among...
Question 103: You are the project manager of the GGK project for your comp...
Question 104: Who is the most appropriate person to conduct a risk identif...
Question 105: When monitoring the execution quality of risk-related plans ...
Question 106: You work as a project manager for TechSoft Inc. You, the pro...
Question 107: What are the supporting elements for effective risk manageme...
Question 108: What items should be included in a complex project's risk ma...
Question 109: Sammy is the project manager for her organization. She would...
Question 110: In addition to monitoring and controlling the project risks ...
Question 111: Which of the following is an example of recommended correcti...
Question 112: Which is a valid response to negative risks?...
Question 113: Where can a project manager find risk-rating rules?...
Question 114: Adrian is the project manager of the NHP Project. In her pro...
Question 115: Which input could be utilized to perform quantitative risk a...
Question 116: During a weekly project review meeting, a stakeholder identi...
Question 117: You are working with your project stakeholders to identify r...
Question 118: What are critical success factors for the Plan Risk Response...
Question 119: You are the project manager of the GYH project for your orga...
Question 120: You are preparing to start the qualitative risk analysis pro...
Question 121: Mike is the project manager of the NNP Project for his organ...
Question 122: David is the project manager of HGF project for his company....
Question 123: Holly is the project manager of the NHQ project for her comp...
Question 124: Ben is the project manager of the CMH Project for his organi...
Question 125: At the completion of a small project, the risk manager perfo...
Question 126: There are seven risk responses, a project manager can use to...
Question 127: You are the project manager for the NHQ Project. This projec...
Question 128: The risk manager is documenting the results of the Monitor R...
Question 129: Shawn is the project manager of the WHT Project for his comp...
Question 130: Fred is the project manager of the PKL project. He is workin...
Question 131: You and your project team have identified the project risks ...
Question 132: Holly is the project manager of the NSS Project for her comp...
Question 133: Your organization has a project that is expected to last 20 ...
Question 134: While preparing for a project review meeting with leadership...
Question 135: To properly ensure risk information is incorporated into the...
Question 136: A project manager must have certain interpersonal skills to ...
Question 137: Bill is the project manager of the JKH Project. He and the p...
Question 138: You are the project manager of the NNQ Project for your comp...
Question 139: While creating the appropriate risk strategy, the project ma...
Question 140: As a part of monitoring and controlling the project, the pro...
Question 141: Della works as a project manager for SoftTech Inc. She is wo...
Question 142: Adrian is a project manager for a new project using a techno...
Question 143: Bill is the project manager for a project that will last six...
Question 144: Which of the following processes is described in the stateme...
Question 145: You work as a project manager for BlueWell Inc. You would li...
Question 146: If a risk has a 20 percent chance of happening in a given mo...
Question 147: The risk manager organizes a stakeholder meeting to obtain a...
Question 148: You are the project manager of the GHQ project for your comp...
Question 149: Frank is the project manager of the NHL Project for his comp...
Question 150: You work as the project manager for Bluewell Inc. Your proje...
Question 151: A part of a project deals with the hardware work. As a proje...
Question 152: You are the project manager of the GHE Project. You have ide...
Question 153: Frances is the project manager of a project in her organizat...
Question 154: Nancy is the project manager of the NHH project. She and the...
Question 155: Which of the following events would result in a baseline upd...
Question 156: You are the project manager of the HJH project for your comp...
Question 157: Which of the following represents the best description of th...
Question 158: During the risk Monitor and Control Project Work process, th...
Question 159: You work as a project manager for BlueWell Inc. You are prep...
Question 160: A project is in the planning phase, and the risk manager est...
Question 161: Examine the figure given below. What will be the expected mo...
Question 162: After years of experience, a project manager becomes the lea...
Question 163: What is risk tolerance?
Question 164: Management has asked you to perform a risk audit and report ...
Question 165: The risk transference is referred to the transfer of risks t...
Question 166: Which of the following will ultimately determine risk thresh...
Question 167: You work as a project manager for SoftTech Inc. You are work...
Question 168: You work as a project manager for BlueWell Inc. You want to ...
Question 169: There are seven risk responses for any project. Which one of...
Question 170: A risk on the risk register is triggered. This triggered ris...
Question 171: You are the project manager of the GHY project. In your orga...
Question 172: Which of the following are parts of SWOT Analysis? Each corr...
Question 173: Della works as a project manager for Tech Perfect Inc. She i...
Question 174: A project risk manager is concerned about the low performanc...
Question 175: You are the project manager of a large construction project....
Question 176: Joan is the project manager of the BTT project for her compa...
Question 177: What best describes the job of a risk owner?...
Question 178: The company board is concerned about potential legal action ...
Question 179: A heavy industrial design firm has over US$3 billion in curr...
Question 180: Eric is the project manager of the MTC project for his compa...
Question 181: You are the project manager of the GGG project. You have com...
Question 182: Mary is the project manager of PKT project. In Mary's projec...
Question 183: You are the project manager for BlueWell Inc. You are review...
Question 184: You are the project manager for your organization and you ar...
Question 185: (Exhibit) Very low = 1, Low = 2, Moderate = 3, High = 4, Ver...
Question 186: The risk manager of a medium-sized project is performing ris...
Question 187: You work as a project manager for TechSoft Inc. You are work...
Question 188: Elizabeth is a project manager for her organization and she ...
Question 189: You are project manager for ABD project. You, with your team...
Question 190: Harry is the project manager of the MMQ Construction Project...