Question 11/73

During project inception an agile practitioner engages the stakeholder to ensure alignment on the project's strategy and vision The stakeholder asks for detailed requirements design, and delivery plans What should the agile practitioner do?

LEAVE A REPLY

Your email address will not be published. Required fields are marked *

Question List (73q)
Question 1: An agile team lead is assigned to a project that must ensure...
Question 2: A team member has spent 5 days on a spike and the first set ...
Question 3: An agile practitioner wants to communicate the effect of tec...
Question 4: A learn using Kanban identifies mat their cycle time has sig...
Question 5: An agile team delivered a feature in the last iteration. The...
Question 6: A learn member 15 stressed due to a heavy workload, while ot...
Question 7: A project manager is concerned that the team has misaligned ...
Question 8: Midway through a sprint. a scrum team member advises the tea...
Question 9: The agile team disagrees with the business stakeholders on c...
Question 10: What estimation technique is an agile team using when collec...
Question 11: During project inception an agile practitioner engages the s...
Question 12: A scrum team has conducted regular retrospectives to discuss...
Question 13: A product owner with experience in a predictive approach wan...
Question 14: During a review session an agile team presented done require...
Question 15: On an agile project some of the development team is struggli...
Question 16: The project team is ahead of schedule and beginning to gold-...
Question 17: The team is in the middle of an iteration and there is an ur...
Question 18: An agile practitioner notices that team members are disengag...
Question 19: After completing the release plan, the team realizes that th...
Question 20: During sprint planning the product owner wants the team to p...
Question 21: During a mature agite team's planning meeting a team member ...
Question 22: During a retrospective the agile practitioner discovers that...
Question 23: A mature agile team welcomes a new member. Due to poor exper...
Question 24: A client slates that a product is not being built as request...
Question 25: A company is moving into a new space and is determining the ...
Question 26: During a current sprint a learn member asks permission horn ...
Question 27: Two teams have received project requirements and completed e...
Question 28: During a team meeting, members who are subject matter expert...
Question 29: Midway through a sprint, a team member discovers that the pr...
Question 30: A newly formed development learn experienced difficulty with...
Question 31: What should an agile practitioner do to ensure that the end ...
Question 32: Two similar stories A and B. are estimated at 3 story points...
Question 33: Team A is working on the second sprint of a product release ...
Question 34: During a project's last few sprints, an agile practitioner n...
Question 35: Why should a project team reduce the work in process?...
Question 36: An agile team is working on the first sprint, and have alrea...
Question 37: While attending a conference, an agile practitioner learns o...
Question 38: During a retrospective, team members suggest process improve...
Question 39: A team is transitioning from a predictive approach to an agi...
Question 40: Stakeholders ate displeased with the latest release o! a pro...
Question 41: While struggling to take ownership of delivery, an agile tea...
Question 42: An agile team has been in place for five years and the custo...
Question 43: A product owner feels that the last sprint tailed to suffici...
Question 44: Outing a review session a customer representative is concern...
Question 45: A new learn member asks what changes could accelerate a chan...
Question 46: During a retrospective meeting, a team develops a large list...
Question 47: A scrum team has eight developers, but only two are database...
Question 48: A new CIO advocates an agile framework for new IT projects, ...
Question 49: A seven-member agile team's composition vanes considerably i...
Question 50: A team is creating a highly marketed, time-sensitive product...
Question 51: A product owner complains that some of the requirements iden...
Question 52: A product owner adds a 21-point. high-priority story to a sp...
Question 53: Due to its complexity, a new team member struggles with deve...
Question 54: During sprint retrospectives, some team members are very voc...
Question 55: Trend analysis shows that velocity is significantly higher t...
Question 56: During its first sprint a new scrum team realizes that it ha...
Question 57: An agile coach is assigned to help a project learn that was ...
Question 58: Following an upgrade, a software support team is overwhelmed...
Question 59: The executive leadership wants to understand ways to better ...
Question 60: What should a Scrum Master do when one team member falls beh...
1 commentQuestion 61: The product owner of a learn starts the iteration review wit...
Question 62: A company president is concerned about the impact of a natur...
Question 63: How can an agile practitioner ensure that all key stakeholde...
Question 64: The agile practitioner has determined that two different tea...
Question 65: During a sprint, the team encounters a technical problem tha...
Question 66: What should a learn do when they complete ail sprint goals e...
Question 67: What role should a servant leader perform to reduce team dis...
Question 68: The amount of information captured in the project's defects ...
Question 69: An agile project manager notices that the product owner mana...
Question 70: A senior team member feels underutilized. What should the ag...
Question 71: Stakeholders have conflicting requirements, and the product ...
Question 72: An agile team is preparing a release plan for a project. Wha...
Question 73: During planning sessions, an agile practitioner notices that...