Online Access Free PMI-ACP Exam Questions

Exam Code:PMI-ACP
Exam Name:PMI Agile Certified Practitioner
Certification Provider:PMI
Free Question Number:73
Version:v2020-12-04
Rating:
# of views:1943
# of Questions views:59690
Go To PMI-ACP Questions

Recent Comments (The most recent comments are at the top.)

Eric - Apr 05, 2022

Thank you guys, just passed PMI-ACP exam.

Penny - Feb 25, 2022

freecram pdf file for PMI PMI-ACP exam is amazing. Includes the best preparatory stuff for PMI-ACP exam. I studied from it for 2-3 days and passed the exam with 92% marks. Great feature by freecram. Highly suggested.

Gavin - Jan 14, 2022

I passed the PMI-ACP exam with flying colors on my first attempt. Really happy with all the help I got from PMI-ACP exam dumps.

Marcus - Jan 01, 2022

I took PMI-ACP exam using freecram study guide. Thanks for your support! Recommend.

Boyce - Dec 27, 2021

Just pass today. This site is the God Sent!
Thanks to freecram for providing the latest dumps that are surely a part of the original exam

Alger - Dec 22, 2021

You are really a good provider. Thank you made me pass PMI Agile Certified Practitioner

Mortimer - Dec 14, 2021

Very similar questions and accurate answers for PMI-ACP certification exam. I would like to recommend freecram to all giving the PMI-ACP exam. Helped me achieve 96% marks.

Mohammad Abu Latifah - Nov 20, 2021

No.# Hi . HOW CAN I GET YOUR PMI ACP EXAM ?

Cornelia - Oct 09, 2021

I candidated PMI-ACP examination last week and passed it pretty easily. Most questions are contained. Only 2 questions is out. All my thanks!

April - Oct 09, 2021

I’m glad that i chose freecram's PMI-ACP practice test, because I passed the PMI-ACP exam with a good score! Thank you so much!

Louise - Jun 15, 2021

There is no need to be nervous, PMI-ACP exam braindumps is a decent study material and you will pass the exam if you have it. I have already gotten my certification. Thanks and all the very best!

LEAVE A REPLY

Your email address will not be published. Required fields are marked *

Other Version
120 viewsPMI.PMI-ACP.v2025-08-23.q342
897 viewsPMI.PMI-ACP.v2023-07-17.q183
1971 viewsPMI.PMI-ACP.v2022-03-31.q145
2830 viewsPMI.PMI-ACP.v2020-12-28.q73
1857 viewsPMI.PMI-ACP.v2020-11-13.q73
1307 viewsPMI.PMI-ACP.v2020-11-11.q73
2894 viewsPMI.PMI-ACP.v2020-10-18.q278
1295 viewsPMI.PMI-ACP.v2020-10-09.q66
1303 viewsPMI.PMI-ACP.v2020-01-16.q65
1913 viewsPMI.PMI-ACP.v2018-04-10.q145
Exam Question List
Question 1: An agile team lead is assigned to a project that must ensure...
Question 2: A team member has spent 5 days on a spike and the first set ...
Question 3: An agile practitioner wants to communicate the effect of tec...
Question 4: A learn using Kanban identifies mat their cycle time has sig...
Question 5: An agile team delivered a feature in the last iteration. The...
Question 6: A learn member 15 stressed due to a heavy workload, while ot...
Question 7: A project manager is concerned that the team has misaligned ...
Question 8: Midway through a sprint. a scrum team member advises the tea...
Question 9: The agile team disagrees with the business stakeholders on c...
Question 10: What estimation technique is an agile team using when collec...
Question 11: During project inception an agile practitioner engages the s...
Question 12: A scrum team has conducted regular retrospectives to discuss...
Question 13: A product owner with experience in a predictive approach wan...
Question 14: During a review session an agile team presented done require...
Question 15: On an agile project some of the development team is struggli...
Question 16: The project team is ahead of schedule and beginning to gold-...
Question 17: The team is in the middle of an iteration and there is an ur...
Question 18: An agile practitioner notices that team members are disengag...
Question 19: After completing the release plan, the team realizes that th...
Question 20: During sprint planning the product owner wants the team to p...
Question 21: During a mature agite team's planning meeting a team member ...
Question 22: During a retrospective the agile practitioner discovers that...
Question 23: A mature agile team welcomes a new member. Due to poor exper...
Question 24: A client slates that a product is not being built as request...
Question 25: A company is moving into a new space and is determining the ...
Question 26: During a current sprint a learn member asks permission horn ...
Question 27: Two teams have received project requirements and completed e...
Question 28: During a team meeting, members who are subject matter expert...
Question 29: Midway through a sprint, a team member discovers that the pr...
Question 30: A newly formed development learn experienced difficulty with...
Question 31: What should an agile practitioner do to ensure that the end ...
Question 32: Two similar stories A and B. are estimated at 3 story points...
Question 33: Team A is working on the second sprint of a product release ...
Question 34: During a project's last few sprints, an agile practitioner n...
Question 35: Why should a project team reduce the work in process?...
Question 36: An agile team is working on the first sprint, and have alrea...
Question 37: While attending a conference, an agile practitioner learns o...
Question 38: During a retrospective, team members suggest process improve...
Question 39: A team is transitioning from a predictive approach to an agi...
Question 40: Stakeholders ate displeased with the latest release o! a pro...
Question 41: While struggling to take ownership of delivery, an agile tea...
Question 42: An agile team has been in place for five years and the custo...
Question 43: A product owner feels that the last sprint tailed to suffici...
Question 44: Outing a review session a customer representative is concern...
Question 45: A new learn member asks what changes could accelerate a chan...
Question 46: During a retrospective meeting, a team develops a large list...
Question 47: A scrum team has eight developers, but only two are database...
Question 48: A new CIO advocates an agile framework for new IT projects, ...
Question 49: A seven-member agile team's composition vanes considerably i...
Question 50: A team is creating a highly marketed, time-sensitive product...
Question 51: A product owner complains that some of the requirements iden...
Question 52: A product owner adds a 21-point. high-priority story to a sp...
Question 53: Due to its complexity, a new team member struggles with deve...
Question 54: During sprint retrospectives, some team members are very voc...
Question 55: Trend analysis shows that velocity is significantly higher t...
Question 56: During its first sprint a new scrum team realizes that it ha...
Question 57: An agile coach is assigned to help a project learn that was ...
Question 58: Following an upgrade, a software support team is overwhelmed...
Question 59: The executive leadership wants to understand ways to better ...
Question 60: What should a Scrum Master do when one team member falls beh...
1 commentQuestion 61: The product owner of a learn starts the iteration review wit...
Question 62: A company president is concerned about the impact of a natur...
Question 63: How can an agile practitioner ensure that all key stakeholde...
Question 64: The agile practitioner has determined that two different tea...
Question 65: During a sprint, the team encounters a technical problem tha...
Question 66: What should a learn do when they complete ail sprint goals e...
Question 67: What role should a servant leader perform to reduce team dis...
Question 68: The amount of information captured in the project's defects ...
Question 69: An agile project manager notices that the product owner mana...
Question 70: A senior team member feels underutilized. What should the ag...
Question 71: Stakeholders have conflicting requirements, and the product ...
Question 72: An agile team is preparing a release plan for a project. Wha...
Question 73: During planning sessions, an agile practitioner notices that...