Question 70/73

At the retrospective, the burndown chart shows that the project is slightly behind schedule. The project team identifies an inexperienced software engineer as the source of reduced velocity-How should the project team address this issue?

LEAVE A REPLY

Your email address will not be published. Required fields are marked *

Question List (73q)
Question 1: The risk profile of a project has increased beyond the upper...
Question 2: An agile team is under pressure to deliver an application. T...
Question 3: Midway through a two-week sprint, an agile team realizes tha...
Question 4: A product owner adds a 21-point. high-priority story to a sp...
Question 5: After completing the release plan, the team realizes that th...
Question 6: Based on the chart, what is the current status of the iterat...
Question 7: An agile project has three more iterations before the releas...
Question 8: Stakeholders ate displeased with the latest release o! a pro...
Question 9: An agile team lead is assigned to a project that must ensure...
Question 10: Agile team A struggles to deliver committed stories due to t...
Question 11: A scrum master is part of a project team using technologies ...
Question 12: A new product owner shares the product vision during the tea...
Question 13: A development team and product owner disagree on a user stor...
Question 14: The team is in the middle of an iteration and there is an ur...
Question 15: A mature agile team welcomes a new member. Due to poor exper...
Question 16: On an agile project some of the development team is struggli...
Question 17: During a team meeting, members who are subject matter expert...
Question 18: A product owner new to the role is very enthusiastic about a...
Question 19: Team A is working on the second sprint of a product release ...
Question 20: A product owner complains that some of the requirements iden...
Question 21: How can a scrum team obtain more feedback from a minimally r...
Question 22: During the implementation of a story, a scrum team notifies ...
Question 23: An agile team and a traditional development team are working...
Question 24: During an iteration planning meeting, the team suggests chan...
Question 25: The product owner wants to build security firewalls into the...
Question 26: What should an agile practitioner do to ensure that the end ...
Question 27: During sprint planning the product owner wants the team to p...
Question 28: A newly formed development learn experienced difficulty with...
Question 29: A legal department representative contacts the scrum master ...
Question 30: Senior management is frustrated at the lack of a detailed im...
Question 31: A member of the development team is working on a prioritized...
Question 32: An agile project leader notices that the team's velocity has...
Question 33: During a daily stand up, the tester engages the developer in...
Question 34: Due to its complexity, a new team member struggles with deve...
Question 35: There is a database feature requiring three members of a sev...
Question 36: A key stakeholder cannot attend the project vision statement...
Question 37: A project manager is concerned that the team has misaligned ...
Question 38: A new agile project manager accepts an assignment to manage ...
Question 39: During a retrospective meeting, a team develops a large list...
Question 40: During sprint planning learn members have differing opinions...
Question 41: A product that recently went to market is receiving a great ...
Question 42: During a mature agite team's planning meeting a team member ...
Question 43: When prioritizing features to be delivered in an iteration, ...
Question 44: During a retrospective the agile practitioner discovers that...
Question 45: A project Worn meets to estimate user stones for a sprint. W...
Question 46: Two teams have received project requirements and completed e...
Question 47: An executive sponsor of a new scrum team actively attends sc...
Question 48: During a review session an agile team presented done require...
Question 49: Outing a review session a customer representative is concern...
Question 50: During planning sessions, an agile practitioner notices that...
Question 51: An agile team delivered a feature in the last iteration. The...
Question 52: How should a project leader manage stakeholder expectations ...
Question 53: A team identifies the number of threats and lists them in th...
Question 54: An agile team member identifies a potential problem within t...
Question 55: A product's scope and acceptance criteria have been defined,...
Question 56: The scrum master for a large project must provide an estimat...
Question 57: More details for a story are required before the upcoming sp...
Question 58: What should a team consider when calculating the effort need...
Question 59: A key stakeholder cannot attend the project vision statement...
Question 60: Following an upgrade, a software support team is overwhelmed...
Question 61: The executive leadership wants to understand ways to better ...
Question 62: A team member has spent 5 days on a spike and the first set ...
Question 63: An agile team is planning the next iteration tor a product r...
Question 64: Prior to a retrospective, discussions among team members ind...
Question 65: A company is considering developing a new, complex applicati...
Question 66: After seeing the planned features for an upcoming release, a...
Question 67: The agile practitioner has determined that two different tea...
Question 68: An agile team is preparing a release plan for a project. Wha...
Question 69: Midway through a sprint. a scrum team member advises the tea...
Question 70: At the retrospective, the burndown chart shows that the proj...
Question 71: During a project review, the team discovers customer feedbac...
Question 72: After a successful product deployment, a key stakeholder inf...
Question 73: What role should a servant leader perform to reduce team dis...