Question 28/73

A newly formed development learn experienced difficulty with accurately estimating product backlog items As a result, the team failed to deliver all of the features in the sprint backlog for the past two iterations What should the team do to improve the accuracy of their estimates?

LEAVE A REPLY

Your email address will not be published. Required fields are marked *

Question List (73q)
Question 1: The risk profile of a project has increased beyond the upper...
Question 2: An agile team is under pressure to deliver an application. T...
Question 3: Midway through a two-week sprint, an agile team realizes tha...
Question 4: A product owner adds a 21-point. high-priority story to a sp...
Question 5: After completing the release plan, the team realizes that th...
Question 6: Based on the chart, what is the current status of the iterat...
Question 7: An agile project has three more iterations before the releas...
Question 8: Stakeholders ate displeased with the latest release o! a pro...
Question 9: An agile team lead is assigned to a project that must ensure...
Question 10: Agile team A struggles to deliver committed stories due to t...
Question 11: A scrum master is part of a project team using technologies ...
Question 12: A new product owner shares the product vision during the tea...
Question 13: A development team and product owner disagree on a user stor...
Question 14: The team is in the middle of an iteration and there is an ur...
Question 15: A mature agile team welcomes a new member. Due to poor exper...
Question 16: On an agile project some of the development team is struggli...
Question 17: During a team meeting, members who are subject matter expert...
Question 18: A product owner new to the role is very enthusiastic about a...
Question 19: Team A is working on the second sprint of a product release ...
Question 20: A product owner complains that some of the requirements iden...
Question 21: How can a scrum team obtain more feedback from a minimally r...
Question 22: During the implementation of a story, a scrum team notifies ...
Question 23: An agile team and a traditional development team are working...
Question 24: During an iteration planning meeting, the team suggests chan...
Question 25: The product owner wants to build security firewalls into the...
Question 26: What should an agile practitioner do to ensure that the end ...
Question 27: During sprint planning the product owner wants the team to p...
Question 28: A newly formed development learn experienced difficulty with...
Question 29: A legal department representative contacts the scrum master ...
Question 30: Senior management is frustrated at the lack of a detailed im...
Question 31: A member of the development team is working on a prioritized...
Question 32: An agile project leader notices that the team's velocity has...
Question 33: During a daily stand up, the tester engages the developer in...
Question 34: Due to its complexity, a new team member struggles with deve...
Question 35: There is a database feature requiring three members of a sev...
Question 36: A key stakeholder cannot attend the project vision statement...
Question 37: A project manager is concerned that the team has misaligned ...
Question 38: A new agile project manager accepts an assignment to manage ...
Question 39: During a retrospective meeting, a team develops a large list...
Question 40: During sprint planning learn members have differing opinions...
Question 41: A product that recently went to market is receiving a great ...
Question 42: During a mature agite team's planning meeting a team member ...
Question 43: When prioritizing features to be delivered in an iteration, ...
Question 44: During a retrospective the agile practitioner discovers that...
Question 45: A project Worn meets to estimate user stones for a sprint. W...
Question 46: Two teams have received project requirements and completed e...
Question 47: An executive sponsor of a new scrum team actively attends sc...
Question 48: During a review session an agile team presented done require...
Question 49: Outing a review session a customer representative is concern...
Question 50: During planning sessions, an agile practitioner notices that...
Question 51: An agile team delivered a feature in the last iteration. The...
Question 52: How should a project leader manage stakeholder expectations ...
Question 53: A team identifies the number of threats and lists them in th...
Question 54: An agile team member identifies a potential problem within t...
Question 55: A product's scope and acceptance criteria have been defined,...
Question 56: The scrum master for a large project must provide an estimat...
Question 57: More details for a story are required before the upcoming sp...
Question 58: What should a team consider when calculating the effort need...
Question 59: A key stakeholder cannot attend the project vision statement...
Question 60: Following an upgrade, a software support team is overwhelmed...
Question 61: The executive leadership wants to understand ways to better ...
Question 62: A team member has spent 5 days on a spike and the first set ...
Question 63: An agile team is planning the next iteration tor a product r...
Question 64: Prior to a retrospective, discussions among team members ind...
Question 65: A company is considering developing a new, complex applicati...
Question 66: After seeing the planned features for an upcoming release, a...
Question 67: The agile practitioner has determined that two different tea...
Question 68: An agile team is preparing a release plan for a project. Wha...
Question 69: Midway through a sprint. a scrum team member advises the tea...
Question 70: At the retrospective, the burndown chart shows that the proj...
Question 71: During a project review, the team discovers customer feedbac...
Question 72: After a successful product deployment, a key stakeholder inf...
Question 73: What role should a servant leader perform to reduce team dis...