Question 66/255

Which earned value management formula can help you determine how likely it is that you'll complete the program based on the amount of cash left in the program budget?

LEAVE A REPLY

Your email address will not be published. Required fields are marked *

Question List (255q)
Question 1: Which of the following statements are true regarding the Mon...
Question 2: During the selection of source process, you assign certain p...
Question 3: Mary has just completed a large program for her organization...
Question 4: Rick is a Program Manager for a large construction program. ...
Question 5: Your program is to construct a new condo building in Chicago...
Question 6: On which of the following documents you work throughout the ...
Question 7: Molly is the program manager for her organization. She is cr...
Question 8: You are the program manager for your organization and are re...
Question 9: You are the program manager of the JNH Program. Tom, a proje...
Question 10: After program closure, the lessons learned document becomes ...
Question 11: You are the program manager for your organization. You have ...
Question 12: Mike is the program manager of the NHQ Program. Mike and a v...
Question 13: You are the program manager for your organization. Managemen...
Question 14: When is the lessons learned document updated?...
Question 15: What is the primary purpose of a project kick-off meeting?...
Question 16: As a program manager you must also understand the project ma...
Question 17: You are the program manager for the BHN Program. Your progra...
Question 18: Which of the following statements are true regarding program...
Question 19: Where are negative risks recorded?...
Question 20: Which of the following is used to build consensus through ro...
Question 21: You are the program manager for your organization and are co...
Question 22: You are the program manager for your organization. You are e...
Question 23: You are the program manager for your organization and are wo...
Question 24: You are the program manager for the HQM Program. Your progra...
Question 25: Tom is program manager for his organization. His program is ...
Question 26: You are the program manager for your organization. Your prog...
Question 27: Your program creates a byproduct that you could sell to a cl...
Question 28: You are the program manager for your organization. Your curr...
Question 29: You are the program manager for your company and management ...
Question 30: You are program manager for the HYH Program. Your program go...
Question 31: You are the program manager for your organization. Your prog...
Question 32: In your organization there are rules and procedures that the...
Question 33: A team member has made a mistake during the installation of ...
Question 34: You are the program manager for your organization and are co...
Question 35: Don is the project manager of the NQP Project for his organi...
Question 36: All of the following are resources that you will need to mon...
Question 37: Part of your job as the program manager is to coach the proj...
Question 38: You are the program manager for your organization. You have ...
Question 39: Which of the following individual should respond to the risk...
Question 40: You are the project manager for the JJY Project, which is si...
Question 41: Joan is the program manager for her organization. Management...
Question 42: When a change enters your program requirements you must upda...
Question 43: You are the program manager for your organization. You are p...
Question 44: Andy is the program manager of the HQN Program. This program...
Question 45: What duration compression technique typically adds risk when...
Question 46: You are the program manager for your organization. You're cu...
Question 47: Kelly's program is slipping on its schedule. Management is w...
Question 48: What is the other name for critical delivery dates?...
Question 49: What percentage of communication is nonverbal?...
Question 50: You work as a program manager for a large construction progr...
Question 51: What does RACI stand for?
Question 52: You need to create a document that will define the costs, re...
Question 53: Part of program management is to identify what motivates you...
Question 54: Which of the following documents is described in the stateme...
Question 55: You are the program manager of the NQA Program. In this prog...
Question 56: Which one of the following is not an output of the direct an...
Question 57: Your program has a budget at completion of $1,550,000 and is...
Question 58: Mary Anne is the program manager for her organization. In he...
Question 59: Robert is the program manager of the NHQ Program. His team h...
Question 60: You are the project manager for the GGG Project and are abou...
Question 61: You are the program manager for your company and are monitor...
Question 62: There are 1,500 doors to be installed in Tom's program. Each...
Question 63: A project manager in your program is using progress elaborat...
Question 64: Which of the following information gathering techniques is d...
Question 65: Paula is program manager for her organization. It has come t...
Question 66: Which earned value management formula can help you determine...
Question 67: There are five stages of team development. At which stage ar...
Question 68: You are the program manager for the NHQ Program. Your progra...
Question 69: At what point in the project is the risk of failing to achie...
Question 70: All of the following are resources that need to be monitored...
Question 71: You are the program manager for your organization. You and y...
Question 72: You are the program manager for the SRQ Program. You have re...
Question 73: You are the program manager of the HNG Program. This program...
Question 74: Which of the following represents the duration of activities...
Question 75: You are the program manager for your organization and are pl...
Question 76: You are the program manager for your organization. A new pro...
Question 77: You are the program manager for your organization that utili...
Question 78: A wild life protection organization opposes your program, wh...
Question 79: You are the program manager for the JQN Program in your orga...
Question 80: You are the program manager for your organization. As your p...
Question 81: What quality control chart compares two or more variables ov...
Question 82: You are the program manager of the BHG Program. One of the p...
Question 83: Hal is the program manager for his organization. He would li...
Question 84: Which of the following can be used to help you or other proj...
Question 85: You are the program manager for your organization. Your curr...
Question 86: Which of the following statements are true regarding program...
Question 87: You are working with Sam, a project manager on one of the pr...
Question 88: June is the program manager for her organization. Management...
Question 89: You are the program manager of the MQQ Program. Your program...
Question 90: You are the program manager of the YHT Program. You have bee...
Question 91: Which of the following statements is most accurate about the...
Question 92: You are the project manager of a construction project. You h...
Question 93: You are the program manager of the NHQ Program. The program ...
Question 94: Which of the following plans should a project manager implem...
Question 95: Which of the following is not a phase of program life cycle?...
Question 96: Which of the following is NOT true regarding the program wor...
Question 97: Which one of the following is the best example of transferen...
Question 98: Which one of the following is not considered one of the thre...
Question 99: What is another term that can be assigned to the pre-program...
Question 100: What cost estimating approach uses the work breakdown struct...
Question 101: Which of the following documents sets the project objectives...
Question 102: You are the program manage of HYH Program for your organizat...
Question 103: An organization supports both programs and projects for vari...
Question 104: All of the following are benefits of a program except for wh...
Question 105: You are the program manager for your organization and you ar...
Question 106: You are the program manager for your organization. Managemen...
Question 107: In which of the following processes is the program charter c...
Question 108: Which of the following contract types is described in the st...
Question 109: You are the program manager for the GHT Program for your com...
Question 110: Which of the following program process outputs includes caus...
Question 111: Harriet is the program manager of a large program that has a...
Question 112: Your program has just been chartered during the program init...
Question 113: Who prepares the statement of work (SOW) for external projec...
Question 114: You have completed a project for a client at his facility. T...
Question 115: You are the project manager for your organization. Your proj...
Question 116: Hans is the program manager for his organization. His curren...
Question 117: What analysis type could you use in a program to compare the...
Question 118: Robert's program is slipping on its schedule and management ...
Question 119: You are the program manager for your organization and your t...
Question 120: An organization is considering a new program. The program ha...
Question 121: An organization is considering a new program. The business a...
Question 122: You are the program manager for a construction program. In t...
Question 123: What should a program manager do when a scope change has bee...
Question 124: Who owns the program?
Question 125: You are the program manager for your organization and are wo...
Question 126: You are the program manager of a new program in your organiz...
Question 127: If a risk has a probability of 60 percent and an impact of -...
Question 128: You are the program manager for the HGQ Program in your orga...
Question 129: A risk response in a project in your program has actually ca...
Question 130: A new program is being initiated for the HNQ Organization. T...
Question 131: Martha is the program manager for her organization. One of t...
Question 132: You are the program manager for your organization and you ne...
Question 133: You are a program manager of a program. You are required to ...
Question 134: You are the program manager of the YGH Program. A vendor has...
Question 135: You are the program manager for your organization and you're...
Question 136: You are coaching Tammy, a project manager in your program, o...
Question 137: Performing quality assurance in a program can result in whic...
Question 138: You are the program manager for a new software development p...
Question 139: What schedule analysis simulation tool allows you, the proje...
Question 140: You are the program manager of the GHY Program in your organ...
Question 141: Which of the following tools and techniques are parts of the...
Question 142: Which one of the following is NOT a component of the risk mo...
Question 143: You are the program manager for your project. You are workin...
Question 144: You are trying to determine if you should buy or build a sol...
Question 145: You are the program manager of the NHQ Program. You will nee...
Question 146: You are the program manager for your organization and you're...
Question 147: What document should you provide to the vendors if you're on...
Question 148: You are the program manager for your organization. Part of y...
Question 149: You are the program manager for your organization and you're...
Question 150: Which of the following risk response planning techniques is ...
Question 151: Which of the following shows the ratio between a task's budg...
Question 152: According to Standard for Program Management, Second Edition...
Question 153: Your program has 121 stakeholders that you'll need to commun...
Question 154: Terri is the program manager for her organization and she's ...
Question 155: What is the formula to determine earned value (EV) for a pro...
Question 156: A project manager in your program has estimated the cost of ...
Question 157: Alice is the project manager of the NHQ Project and is enter...
Question 158: You are the program manager for your organization. Your prog...
Question 159: Which of the following documents contain a list of all probl...
Question 160: What document asks the seller to provide your project with a...
Question 161: What does CPI value less than 1.0 indicates?...
Question 162: Robert is the program manager for his organization which ope...
Question 163: You are the program manager for the HNY Corporation and you ...
Question 164: The ____ quality assurance technique ensures continuous impr...
Question 165: You are the program manager for your organization. Managemen...
Question 166: What component of the change management system is responsibl...
Question 167: Your program exists within a matrix structure. Your program ...
Question 168: Communication is large percentage of program execution as th...
Question 169: Wanda is the program manager for her organization. Her progr...
Question 170: Josh is the program manager for his organization and he's le...
Question 171: In your program you must adhere to Six Sigma as part of your...
Question 172: Holly is the program manager for her program. She is creatin...
Question 173: What is a stakeholder analysis chart?...
Question 174: Your program has been selected and its program charter is no...
Question 175: You are the project manager for your organization and are wo...
Question 176: You are the program manager for your organization and are wo...
Question 177: You are the program manager for your organization. Your curr...
Question 178: You are the program manager for your organization. Managemen...
Question 179: You are the program manager for your program and are creatin...
Question 180: Which of the following directs the improvement efforts to th...
Question 181: You are the program manager for your organization. You're cu...
Question 182: Joan is the program manager for her organization. Throughout...
Question 183: You are hosting a meeting with all of the vendors that have ...
Question 184: Which of the following is not a template element that is des...
Question 185: You are the program manager for your organization. Your prog...
Question 186: You are the program manager of the GHY Program. Your program...
Question 187: You are the program manager for your organization. Your prog...
Question 188: A program has a budget at completion of $1,250,000 and has a...
Question 189: You are the program manager for your organization and are pl...
Question 190: You are the program manager for your company and evaluating ...
Question 191: You are the program manager for your organization. Managemen...
Question 192: You are the program manager for your organization. This prog...
Question 193: A program has a BAC of $1,750,000 and is expected to last tw...
Question 194: You are the program manager of the OFE Program. You are work...
Question 195: You are the program manager for your organization and you ar...
Question 196: You are the program manager for your organization. Your prog...
Question 197: Who makes Go/No-Go decisions during phase gate reviews?...
Question 198: What project management term would you associated with a pre...
Question 199: Which of the following types of floats are available? Each c...
Question 200: Julie is the project manager of the NHQ Project. She and her...
Question 201: Martha is sharing her experience of her last project as the ...
Question 202: Two project managers in your program, Marcy and Mary, are no...
Question 203: You are the program manager for a large program in your matr...
Question 204: Your program will create new software and install new hardwa...
Question 205: Ben is the program manager for his organization. He's workin...
Question 206: Identify the term described in the statement given below? "T...
Question 207: Which benefit measurement method considers the value of each...
Question 208: Ned is the program manager for his organization and he's con...
Question 209: Paul is the program manager for his company. He along with h...
Question 210: A knowledge area defines a subset of program management and ...
Question 211: You are the program manager for your organization. Your curr...
Question 212: Which one of the following is the best definition of program...
Question 213: You are the program manager for your organization and are wo...
Question 214: Which project management meeting allows stakeholders to meet...
Question 215: You are the program manager for your organization and are wo...
Question 216: Tom is the program manager for his organization. He has to b...
Question 217: Small changes that bypass the organization's change control ...
Question 218: You are the program manager of the NHQ Program. You are work...
Question 219: Your program has a budget at completion of $1,550,000 and is...
Question 220: Complete the following phrase about quality management: Qual...
Question 221: You are identifying stakeholders for your program to create ...
Question 222: You are a program manager for an environmental program. The ...
Question 223: You are the program manager of the NHQ Program for your orga...
Question 224: Which of the following tools/techniques keep program manager...
Question 225: You have created a control chart for a repeatable process in...
Question 226: You are the program manager for your organization and manage...
Question 227: Part of program management is to understand how the communic...
Question 228: Olive is the program manager for her organization. She has c...
Question 229: Over the life of your program you've received many change re...
Question 230: You are the program manager of the HNG Program. This program...
Question 231: You are the program manager for your organization. One of th...
Question 232: Donna is the project manager for her organization. She is pr...
Question 233: Which of the following is responsible to sign off on the clo...
Question 234: You are the program manager of the HNG Program. This program...
Question 235: You are the program manager for your organization and are ab...
Question 236: Which of the following documents describes the details for e...
Question 237: Your company and a competing company have created a teaming ...
Question 238: You are the program manager for your organization and you ar...
Question 239: You are a program manager for a large construction program. ...
Question 240: You are the program manager for your organization. Managemen...
Question 241: Management is trying to determine which program to initiate....
Question 242: Wan is the program manager for his organization. He has been...
Question 243: Leigh is working with the project stakeholders to define the...
Question 244: Which of the following is described in the statement given b...
Question 245: You are the program manager for your organization and are pl...
Question 246: Gary is program manager for his organization. His current pr...
Question 247: Julie is the program manager of the NHQ Program for her orga...
Question 248: You are a program manager for your organization. You have pr...
Question 249: Program management has several themes that the program manag...
Question 250: You are the program manager for your organization and workin...
Question 251: Which of the following terms is used for a schedule compress...
Question 252: Part of your job as the program manager is to coach the proj...
Question 253: Which of the following increases when one fast tracks the pr...
Question 254: Gary is the program manager for his organization. His curren...
Question 255: If a program has a budget of completion of $550,000, is 25 p...