Valid PgMP Dumps shared by ExamDiscuss.com for Helping Passing PgMP Exam! ExamDiscuss.com now offer the newest PgMP exam dumps, the ExamDiscuss.com PgMP exam questions have been updated and answers have been corrected get the newest ExamDiscuss.com PgMP dumps with Test Engine here:
Andy is the program manager of the HQN Program. This program is nearing its completion and there is still $25,000 left in the program budget. Andy has asked the program team to identify some extra deliverables that can be included in the program scope to improve the program deliverable but also to use all of the funds in the budget. What term is assigned to the actions that Andy is trying to do in this instance?