Who defines the amount of work to be completed during an iteration?
Correct Answer: C
In Disciplined Agile, the amount of work to be completed during an iteration is defined by the team members themselves, based on their understanding of their current capacity and velocity. The team collaboratively estimates what they can achieve and commits to completing that work. Option A (the Product Owner) is responsible for prioritizing the backlog but does not dictate the amount of work. Option B (the team lead) facilitates the process but does not decide the work. Option D (the quality tester) is involved in testing completed work but does not determine the iteration's workload. Top of Form Bottom of Form