Valid ISO-9001-Lead-Auditor Dumps shared by ExamDiscuss.com for Helping Passing ISO-9001-Lead-Auditor Exam! ExamDiscuss.com now offer the newest ISO-9001-Lead-Auditor exam dumps, the ExamDiscuss.com ISO-9001-Lead-Auditor exam questions have been updated and answers have been corrected get the newest ExamDiscuss.com ISO-9001-Lead-Auditor dumps with Test Engine here:
A small deaning services organisation is about to start work on a hospital dleaning contract for the local Health Trust. You, as auditor, are conducting a Stage 2 audit to ISO 9001 and review the contract with the Service Manager. The contract requires that a cleaning plan is produced. You: "How was the cleaning plan for the contract developed?" Service Manager: "We have a basic template that covers the materials, labour requirements and cleaning methods to be employed. Some of that is specified by the customer." You: "How does the plan deal with locations like the intensive care wards and the operating theatres, which are included in the contract?" Service Manager: "The basic plan covers general wards, but we will do more frequent cleaning in those areas if the hospital requests it." You: "Are you aware of the regulatory requirements for cleaning standards in hospitals?" Service Manager: "No. We depend on the hospital to look after that side of things in the contract." You decide to raise a non-conformity against section 8.2.2.a.1 of ISO 9001. You decide to raise another non-conformity against section 8.2.4 of ISO 9001 when finding that the cleaning plan was amended without the agreement of the Health Trust. A different cleaning chemical was substituted to that specified in the contract. At the follow- up audit, the corrective action proposed was to "obtain a concession from the Health Trust for use of the new chemical." Which one of the following options is the reason why you did not accept this action taken?
Correct Answer: D
* Clause 8.2.4 of ISO 9001:2015 - Changes to Requirements for Products and Services:ISO 9001: 2015 Clause 8.2.4 states that when changes to requirements for products or services are made, they must be communicated and agreed upon with relevant interested parties (in this case, the Health Trust). The lack of communication and agreement for substituting the cleaning chemical represents a clear violation of this clause. * Analysis of the Corrective Action Proposed:The organization proposed "obtaining a concession from the Health Trust for the use of the new chemical." This action is reactive and assumes approval from the Health Trust without addressing the systemic issue: the lack of a defined change control process for managing contract changes. * Option Analysis: * A. The substitute chemical has not been used before in the Health Trust:Incorrect. While this may be a concern, it is not directly relevant to the root cause of the nonconformity, which is the absence of a process to handle contract changes. * B. The action assumes that the Health Trust will agree to the change:Incorrect. Although this is true, it is not the primary issue. The nonconformity lies in the lack of a structured approach to obtain agreement, not whether the Health Trust agrees. * C. Staff have not been trained in the use of the new chemical:Incorrect. This is a separate issue related to staff competence (Clause 7.2), but it is not the main reason why the corrective action is unacceptable under Clause 8.2.4. * D. The process for making changes to the contract has not been addressed:Correct. The fundamental issue is the organization's failure to follow or establish a change control process for amending contracts, including gaining formal agreement from the Health Trust. The proposed corrective action does not ensure that such issues will be systematically prevented in the future. * E. The substitute chemical may not be as effective as the original:Incorrect. The effectiveness of the substitute chemical is secondary to the primary issue, which is the lack of a change management process. * ISO 9001 References Supporting the Correct answer: * Clause 8.2.4: Requires that changes to product/service requirements be reviewed, communicated, and agreed upon with the customer. * Clause 10.2 (Nonconformity and Corrective Action): Requires the organization to address the root cause of the nonconformity and take actions to ensure it does not recur. In this case, the root cause is the absence of a change control process. * Why D is the Best answer:The core issue is that the organization did not have a formalized process for managing and agreeing upon changes to contract requirements. Addressing this process gap is essential to prevent recurrence of similar nonconformities. Merely seeking a concession from the Health Trust is a one-off solution that does not address the systemic issue.