While most field resources for a particular company should see the countdown that displays the estimated time remaining for an activity in Oracle Field Service Cloud (OFSC), their 'contractor resources' that only perform periodica work should NOT see it.
Which configuration supports the requirement to hide the countdown timer for those 'contractor resources' that do NOT need to see it when they are working on their assigned activities?
Recent Comments (The most recent comments are at the top.)
Set the visibility condition for the Activity Timer context to 'show* for the User Types that need it, but exclude the ones assigned to the 'contractor resources'.