Valid 1z0-1057-22 Dumps shared by ExamDiscuss.com for Helping Passing 1z0-1057-22 Exam! ExamDiscuss.com now offer the newest 1z0-1057-22 exam dumps, the ExamDiscuss.com 1z0-1057-22 exam questions have been updated and answers have been corrected get the newest ExamDiscuss.com 1z0-1057-22 dumps with Test Engine here:
Your customer started operations and all projects in January 2015. They implemented Enterprise Project Structure for calculating project labor demand by using the Annual option. When they view the labor demand on 15-Dec-2015, the project hierarchy viewer shows data only for the year 2015. The client expected the demand to be shown for a year, from 15-Dec-2015 to 15-Dec-2016. Identify how the project hierarchy viewer displays labor demand information. (Choose the best answer.)
Correct Answer: B
Ref: https://docs.oracle.com/en/cloud/saas/project-portfolio-management/19a/oapem/analyze-project-management-performance.html#OAPEM1313471 Topic - Project Labor Demand: How It's Calculated Settings That Affect Project Labor Demand Project application administrators must do the following to set up how project labor demand is calculated: Organize projects into hierarchical groups on the Manage Enterprise Project Structure page. Change the quarterly FTE hours for the organization on the Define Project Management Implementation Options page, if different from 520 hours. Note: You can choose to view labor demand annually instead of quarterly. The Project Hierarchy Viewer uses the current date to determine which year or quarter to display.