Valid 1z0-1057-22 Dumps shared by ExamDiscuss.com for Helping Passing 1z0-1057-22 Exam! ExamDiscuss.com now offer the newest 1z0-1057-22 exam dumps, the ExamDiscuss.com 1z0-1057-22 exam questions have been updated and answers have been corrected get the newest ExamDiscuss.com 1z0-1057-22 dumps with Test Engine here:
Your company creates a separate project for infrastructure services, so as to track these costs separately and then allocate to various projects that use the services of the infrastructure team. You want to allocate these costs by first attributing a fixed percentage of the source amount to each project and then spread it across tasks based on the actual labor hours charged to each task. Which allocation basis method would you use to meet this requirement? (Choose the best answer.)
Correct Answer: B
Ref: https://docs.oracle.com/en/cloud/saas/project-portfolio-management/19a/oapjc/allocate-project-costs.html#OAPJC94831 Spread Evenly The allocation rule divides the source pool amount equally among all the chargeable target tasks included in the rule. This is the most simple and direct basis method. Target Percentage and Spread Evenly Specify the percentage of the source pool that is required to allocate to each target line. The total specified target percentage must always equal 100 percent. The allocation rule calculates the amount to allocate to the target line, and then spreads the results evenly among the chargeable tasks. Prorate The allocation generation uses the attributes defined in the allocation rule to derive the rate at which the source pool amount is apportioned among the target projects and tasks. For this basis method, the allocation rule uses the basis attributes to apportion the source amount among all the tasks defined by the rule. The Prorate basis method provides precise control over how the rule distributes the source pool. Target Percentage and Prorate The allocation rule first uses the target percentage to calculate the amount to allocate to the line, and then apportions the results among all the tasks. The Target Percentage and Prorate basis method provides precise control over how the rule distributes the source pool.