Valid 1Z0-1057-21 Dumps shared by ExamDiscuss.com for Helping Passing 1Z0-1057-21 Exam! ExamDiscuss.com now offer the newest 1Z0-1057-21 exam dumps, the ExamDiscuss.com 1Z0-1057-21 exam questions have been updated and answers have been corrected get the newest ExamDiscuss.com 1Z0-1057-21 dumps with Test Engine here:
Your customer wants to calculate Estimate to Complete (ETC) as the difference between Current Planned Cost andActual Cost. In Progress Settings, which option would you use in conjunction with the ETC method to meet this requirement? (Choose the best answer.)
Correct Answer: B
Explanation Reference: https://ppm-help.saas.hpe.com/en/9.42/Help/Content/UG/PjMUG/view_pj_cost_data_costtab.htm Below is an example of the Financial Summary view on the Costtab of the Project Overview page. https://admhelp.microfocus.com/ppm/en/9.42/Help/Content/UG/PjMUG/images/ProjectOverviewPage_CostTab