Valid 1Z0-1057-21 Dumps shared by ExamDiscuss.com for Helping Passing 1Z0-1057-21 Exam! ExamDiscuss.com now offer the newest 1Z0-1057-21 exam dumps, the ExamDiscuss.com 1Z0-1057-21 exam questions have been updated and answers have been corrected get the newest ExamDiscuss.com 1Z0-1057-21 dumps with Test Engine here:
When scheduling the Update Project Performance Data process to run on a periodic basis, whichsummarization method would you select? (
Correct Answer: C
Explanation Reference: https://docs.oracle.com/en/cloud/saas/project-portfolio-management/19b/oapfm/define-project-organiz Settings That Affect Performance Data Summarization You can summarize performance data for a project unit, business unit, a range of projects, or projects managed by a project manager. When you run the Update Project Performance Data process from the Scheduled Processes page, select one of the summarization methods from the following table: Summarization Method Usage Incremental Summarizes new transactions that are yet to be summarized Delete and re-summarize Correct summary data when the source system data changes outside the regular transaction flow. Do not use this summarization method when you run the UpdateProject Performance Data Without Producing Report process unless you are advised to do so. Resource breakdown structure Migrate all summary data from one resource breakdown structure version to the next. If you select this option, you must also specify the resource breakdown structure header.