Valid MB-320 Dumps shared by ExamDiscuss.com for Helping Passing MB-320 Exam! ExamDiscuss.com now offer the newest MB-320 exam dumps, the ExamDiscuss.com MB-320 exam questions have been updated and answers have been corrected get the newest ExamDiscuss.com MB-320 dumps with Test Engine here:
A customer produces light projection toys for holiday decorations throughout the year. You are in the first month of a season. Production flows take one day to complete. The floor supervisor reports that seasonal production targets will not be met. You review the Kanban schedule board and identify thousands of unplanned jobs. You need to plan the jobs to be completed two weeks prior to the start of the next season. What are two possible ways to achieve this goal? Each correct answer presents a complete solution. NOTE: Each correct selection is worth one point.
Correct Answer: B,D
Section: Create, process, and manage production batch orders Explanation/Reference: https://docs.microsoft.com/en-us/dynamics365/supply-chain/production-control/lean-manufacturing-kanban- job-scheduling