You are a project manager who uses Project Professional 2013.
You work on a construction project that requires propane as a fuel source for your equipment. The foreman requires that you enter project costs associated with all work completed on your project.
The propane costs $5.00 per gallon, and the tank holds 500 gallons of propane. Each time the tank is refilled, you must pay a fee of $20.
You need to enter the propane costs into your project schedule prior to filling the propane tank for the first time.
What should you do?