Question 36/67

You are a project manager who uses Project Professional 2013.
When viewing the critical path, you notice that there are some inconsistencies. To investigate the status of the critical path, you insert the Total Slack column into a task table. You discover that many of the tasks have negative Total Slack values.
You need to resolve the negative Total Slack values.
What should you do?

LEAVE A REPLY

Your email address will not be published. Required fields are marked *

Question List (67q)
Question 1: You are a project manager for a company that is based in New...
Question 2: You are a project manager who uses Project Professional 2013...
Question 3: You are tracking a project schedule by using Microsoft Proje...
Question 4: Your company uses Project Professional 2013. An organization...
Question 5: You are a project manager who uses Project Standard 2013. Yo...
Question 6: You are a project manager who uses Microsoft project. Your m...
Question 7: You are a project manager, and you successfully complete a s...
Question 8: You are a project manager who uses Project Professional 2013...
Question 9: You are a project manager for a company that uses Project Pr...
Question 10: You are using Project Standard 2013. Management wants to see...
Question 11: You create a new schedule by using Microsoft Project. All ca...
Question 12: Your organization uses Project Professional 2013. A senior s...
Question 13: You are a project manager for an organization that uses Proj...
Question 14: Your company uses Project Professional 2013. You are setting...
Question 15: You are a project manager in an organization that uses Proje...
Question 16: You are managing a project by using Project Professional 201...
Question 17: You are a project manager who uses Project Standard 2013, an...
Question 18: You are a project manager who uses Project Professional 2013...
Question 19: You are a project manager for a company that uses baselines ...
Question 20: You are a senior project manager, and your organization uses...
Question 21: You are a project manager, and you use Project 2013 for a la...
Question 22: You are a project manager who uses Project Standard 2013. Yo...
Question 23: You are a project manager, and your organization uses Projec...
Question 24: Your company uses Project Professional 2013. You are schedul...
Question 25: You are a project manager who uses Project Professional 2013...
Question 26: You are a manager for an organization that uses Project Prof...
Question 27: You are a project manager who uses Project Standard 2013. Yo...
Question 28: You manage a project by using Project Standard 2013. You nee...
Question 29: While scheduling with Project Professional 2013 you notice t...
Question 30: Your company uses Project Professional 2013. You have two pr...
Question 31: You manage a project by using Project Professional 2013. The...
Question 32: You are project manager who uses Project Professional 2013. ...
Question 33: You are a project manager for a large telecommunications com...
Question 34: You are using Microsoft Project Professional 2013. Three yea...
Question 35: You are managing a project using Project Professional 2013. ...
Question 36: You are a project manager who uses Project Professional 2013...
Question 37: You are a project manager who uses Project Professional 2013...
Question 38: You use Project Professional 2013 to manage a project for yo...
Question 39: Your company uses Project Professional 2013, and you are set...
Question 40: You are a project manager and have built a project plan by u...
Question 41: You are a project manager who uses Project Professional 2013...
Question 42: You are a project manager who uses Project Professional 2013...
Question 43: You are a program manager. Your project managers use Project...
Question 44: You are a project manager for an organization that uses Proj...
Question 45: Your company uses Project Professional 2013. You are a progr...
Question 46: You are a project manager who uses Project Standard 2013. Yo...
Question 47: You are an independent project manager who uses Project Prof...
Question 48: You are a project manager who uses Project Standard 2013. Yo...
Question 49: You are a project manager who uses Project Professional 2013...
Question 50: Your company uses Project Professional 2013. You are buildin...
Question 51: Your company uses Microsoft Project, and you are setting up ...
Question 52: You are a project manager who uses Project Professional 2013...
Question 53: You are a project manager for a company that uses Project Pr...
Question 54: Your project managers manage several projects using Project ...
Question 55: You are a project manager for a software development company...
Question 56: You are a project manager who uses Project Professional 2013...
Question 57: You are using Project Standard 2013. You want the ability to...
Question 58: Your organization uses Project Professional 2013. You are se...
Question 59: Your company uses Project Professional 2013. You have severa...
Question 60: You are a project manager who uses Project Standard 2013. A ...
Question 61: Your organization uses Microsoft Project 2013. You are final...
Question 62: You manage a project by using Project Professional 2013. A c...
Question 63: You are a project manager for an organization that uses Proj...
Question 64: You are a project manager, and your organization uses Projec...
Question 65: You use Project Professional 2013 to manage a project schedu...
Question 66: You use Project Professional 2013 to manage a project that h...
Question 67: You are a project manager who uses Project Professional 2013...