Valid CTAL-TTA Dumps shared by ExamDiscuss.com for Helping Passing CTAL-TTA Exam! ExamDiscuss.com now offer the newest CTAL-TTA exam dumps, the ExamDiscuss.com CTAL-TTA exam questions have been updated and answers have been corrected get the newest ExamDiscuss.com CTAL-TTA dumps with Test Engine here:
A project to replace your company's sales and merchandising system has begun. The old system is still in production but is poorly documented and expensive to maintain: changing it has often produced a large quantity of defects. The new version will be developed using modern techniques and technology. Requirements include: * Loading sales data, sent electronically from the stores each evening, into a central database where it is then available for other applications. * Producing sales reports for the merchandisers, whose job is to manage stock levels in stores. * Predictions of future demand for each product, based on a combination of sales history and forecasting parameters. Requirements 1 and 2 are satisfied by the existing system and will be rewritten with no significant changes. Requirement 3 is new: these forecasting reports will be run overnight, and users will request them by entering simple parameters online during the day. The sales data are loaded in an overnight batch run. There have been problems at peak periods when this run has taken longer than scheduled, so that dependent jobs could not finish before the start of the working day. As a Technical Test Analyst, you have been asked to contribute to the project's Master Test Plan. The key stakeholders are: * The Merchandising Manager, who wants parameter entry to be quick and easy. * The Data Centre Manager, who requires the new batch jobs to take less time than the old ones. No specific performance requirements have been given, either for the batch jobs or for online parameter entry. Which TWO of the following will BEST meet the objectives of the stakeholders?
Correct Answer: A,B
In this scenario, the key stakeholders have expressed concerns related to performance, specifically in terms of the batch jobs and the ease of parameter entry for forecasting reports. Given these requirements, performance testing is essential to meet their objectives. Objectives of the Stakeholders: * Merchandising Manager: Wants parameter entry to be quick and easy. * Data Centre Manager: Requires the new batch jobs to take less time than the old ones. Best Testing Approaches: * Performance Testing on Forecasting Report Parameter Data Entry Features (Option A): * Conducting performance testing on the parameter data entry features ensures that the process is quick and efficient, meeting the Merchandising Manager's requirement for ease of use. * Performance Testing on Data Load and Report Creation (Option B): * Conducting performance testing on data load and report creation will address the Data Centre Manager's concern by ensuring that the batch jobs complete in less time compared to the old system. Explanation of Incorrect Options: * C. Agreeing acceptance criteria for modifiability, modularity, and reusability: These criteria are more related to code quality and maintainability rather than performance, which is not the primary concern of the stakeholders. * D. Agreeing acceptance criteria for performance based on quantified improvement: While this is important, it's not a testing activity itself but rather a prerequisite to performance testing. * E. Agreeing acceptance criteria based on operational profile models: This is also more related to planning and less about direct testing activities. References: The ISTQB CTAL-TTA syllabus outlines the importance of performance testing and stakeholder requirements in test planning and execution. Ensuring that performance tests are aligned with the key stakeholder objectives is crucial for successful project outcomes. Sources: * ISTQB-CTAL-TTA Syllabus * General knowledge on performance testing and stakeholder requirement analysis.