Which of the following statements is TRUE with respect to TMMi Levels 4 and 5 in an Agile context?
Correct Answer: D
In an Agile context, some practices from TMMi levels 4 and 5 might be considered less relevant or adjusted to fit the Agile methodology. Specifically, at TMMi level 5, testing with statistical methods may indeed be less relevant. In Agile projects, operational profiles or usage models, which are essential to perform statistically valid testing, are often not utilised. Agile methodologies focus more on incremental development and continuous feedback loops, which do not typically rely on statistical sampling methods. Therefore, the statement that "Agile projects normally do not use operational profiles or usage models of a product on which to base statistically valid inferences to help create a representative sample of tests, thus the TMMi level 5 specific goal 'Testing is performed using Statistical Methods' is considered not relevant in an Agile context" is true.