Valid TMMi-P_Syll2.1 Dumps shared by ExamDiscuss.com for Helping Passing TMMi-P_Syll2.1 Exam! ExamDiscuss.com now offer the newest TMMi-P_Syll2.1 exam dumps, the ExamDiscuss.com TMMi-P_Syll2.1 exam questions have been updated and answers have been corrected get the newest ExamDiscuss.com TMMi-P_Syll2.1 dumps with Test Engine here:
During a TMMi assessment the percentage of process achievement for the Test Planning process area has been determined at 40%. Which of the following compliance ratings would you assign to Test Planning?
Correct Answer: B
With a 40% achievement in the Test Planning process area, the rating would be "Partly achieved." According to TMMi, a process area is rated "Partly achieved" when the percentage of achievement is between 15% and 50%. This indicates that some practices have been implemented, but significant improvement is still required to meet the full requirements of the process area. Reference: "Achievement levels like 'Partly achieved' correspond to percentage ranges, with 40% falling under the 'Partly achieved' category".