Valid CTFL_Syll_4.0 Dumps shared by ExamDiscuss.com for Helping Passing CTFL_Syll_4.0 Exam! ExamDiscuss.com now offer the newest CTFL_Syll_4.0 exam dumps, the ExamDiscuss.com CTFL_Syll_4.0 exam questions have been updated and answers have been corrected get the newest ExamDiscuss.com CTFL_Syll_4.0 dumps with Test Engine here:
Consider the following examples of risks identified in different software development projects: [I]. It may not be possible to generate the expected workloads to run performance tests, due to the poor hardware equipment of the machines (load injectors) that should generate these workloads [II]. A user's session on a web application is not invalidated after a certain period of inactivity (configured by the system administrator) of the user [III]. The test team will not have an adequate requirements specification (since many requirements will still be missing) by the time test design and analysis activities should begin according to the test plan [IV]. Following a failure, the system is unable to continue to maintain its pre-failure operation and some data becomes corrupted Which of the following statements is true?
Correct Answer: A
Product Risks: Relate to the quality of the software product itself, such as functionality, performance, security, and user experience. * II: A session management issue affects the product's security and functionality. * IV: Inability to maintain operation and data corruption directly affects the product's reliability and data integrity. Project Risks: Relate to the circumstances and activities within the project, such as schedule, resources, and planning. * I: Poor hardware equipment for performance testing impacts the project's ability to conduct performance tests. * III: Inadequate requirement specifications affect the project timeline and the ability to design tests.