Valid CTFL-Foundation Dumps shared by ExamDiscuss.com for Helping Passing CTFL-Foundation Exam! ExamDiscuss.com now offer the newest CTFL-Foundation exam dumps, the ExamDiscuss.com CTFL-Foundation exam questions have been updated and answers have been corrected get the newest ExamDiscuss.com CTFL-Foundation dumps with Test Engine here:
Refer to the exhibit The following test cases need to be run, but time is limited, and it is possible that not all will be completed before the end of the test window The first activity is to run any re-tests, followed by the regression test script. Users have supplied their priority order to tests. Which of the following gives an appropriate test execution schedule, taking account of the prioritisation and other constraints?[K3]
Correct Answer: B
The appropriate test execution schedule considering the prioritization and constraints should start with re-tests, followed by the regression test script. After these, tests should be run based on their priority levels: * a (Re-test defect no 52, Low priority, Re-test) * c (Re-test defect no 26, High priority, Re-test) * d (Run regression test script, Medium priority, Regression) * b (Ability to amend transaction type, High priority) * g (Reprint selected previous sales figures, High priority, Must be run after item e) * e (Print monthly sales figures, Medium priority) * i (Print year-to-date figures, Medium priority) * f (Add special invoice to previous month, Low priority) * h (Account administrator able to amend any previous month's sales figures, Low priority) This sequence ensures that re-tests and high-priority tasks are completed first, followed by medium-priority tasks, and then low-priority tasks. Reference: The provided prioritization and constraints are aligned with standard test execution scheduling practices as discussed in the ISTQB CTFL Syllabus, version 4.0.