Question 21/23

Test Management
You are managing the system testing for a SOA based system. The integrated system consists of several subsystems:
- a SOA middleware
- a CRM (Customer Relationship Management) system
- a BRM (Billing and Revenue Management) system
- a SMS (Subscriber Management System) system
and you performed a risk analysis based on these subsystems.
At the end of the scheduled period for test execution you produce a first classical report based on the traditional metrics of testing. Test pass/fail status and bug status (open/resolved) That table provides you a distorted picture of the quality risk, because there is no indication of the risk level of the failed tests, the tests not run, or the open bugs. Thus, you produce the following table to solve this distortion issue:

In the table above, where you have introduced the concept of risk weighting, the highest risk test or bug report has a score of 1, while the lowest risk test or bug report has a score of 0.04.
Which of the following subsystems, based on the risk scores of the table, is most risky?
Number of correct responses: 1
K4 3 credits

LEAVE A REPLY

Your email address will not be published. Required fields are marked *

Question List (23q)
Question 1: Test Management Assume you have some data related to confirm...
Question 2: Assume that no additional product risks have been identified...
Question 3: You can count on well-written requirements, but you can't co...
Question 4: People Skills - Team Composition Consider the following anal...
Question 5: Test Management Consider an agile team adopting Extreme Prog...
Question 6: Test Management Which of the following statements about mana...
Question 7: Test Management Assume you are currently working on a projec...
Question 8: Which of the following statements represents the most effect...
Question 9: Test Management You are the Test Manager of a new project th...
Question 10: People Skills - Team Composition An agile development team d...
Question 11: During the follow-up phase the following conditions are chec...
Question 12: Test Tools and Automation Assume you are managing a test aut...
Question 13: Test Management Which of the following answers describes a f...
Question 14: Defect Management Consider a defect report and assume that a...
Question 15: Test Management Which one of the following metrics to be pro...
Question 16: Test Management You are performing a quality risk analysis f...
Question 17: People Skills - Team Composition Your test team consists of ...
Question 18: Testing Process Which of the following is an example of the ...
Question 19: Improving the Testing Process Consider the following stateme...
Question 20: Test Management Based on the historical data of 5 past and s...
Question 21: Test Management You are managing the system testing for a SO...
Question 22: Testing Process The following are the exit criteria describe...
Question 23: People Skills - Team Composition Assume you are managing the...