Based on the historical data of 5 past and similar projects, you have calculated these average numbers of defects detected in system testing:
- for each 10000 LOC (lines of code), 200 defects
- for each person-month of development team effort, 49 defects
You want to use this information to perform estimation for a new project.
The project manager tells you that he/she has estimated 20000 new LOC for this new project.
Four developers work for four months on this project before system testing.
During system testing, 797 defects are discovered.
Assume that the system test of this new project is using the same amount of work as spent in the past projects.
Based on this information only, which of the following statement is certainly true about this project?
Number of correct responses: 1
K3 3 credits

LEAVE A REPLY

Your email address will not be published. Required fields are marked *

Question List (23q)
Question 1: Test Management Assume you have some data related to confirm...
Question 2: Assume that no additional product risks have been identified...
Question 3: You can count on well-written requirements, but you can't co...
Question 4: People Skills - Team Composition Consider the following anal...
Question 5: Test Management Consider an agile team adopting Extreme Prog...
Question 6: Test Management Which of the following statements about mana...
Question 7: Test Management Assume you are currently working on a projec...
Question 8: Which of the following statements represents the most effect...
Question 9: Test Management You are the Test Manager of a new project th...
Question 10: People Skills - Team Composition An agile development team d...
Question 11: During the follow-up phase the following conditions are chec...
Question 12: Test Tools and Automation Assume you are managing a test aut...
Question 13: Test Management Which of the following answers describes a f...
Question 14: Defect Management Consider a defect report and assume that a...
Question 15: Test Management Which one of the following metrics to be pro...
Question 16: Test Management You are performing a quality risk analysis f...
Question 17: People Skills - Team Composition Your test team consists of ...
Question 18: Testing Process Which of the following is an example of the ...
Question 19: Improving the Testing Process Consider the following stateme...
Question 20: Test Management Based on the historical data of 5 past and s...
Question 21: Test Management You are managing the system testing for a SO...
Question 22: Testing Process The following are the exit criteria describe...
Question 23: People Skills - Team Composition Assume you are managing the...