Valid CTAL-TM_Syll2012 Dumps shared by ExamDiscuss.com for Helping Passing CTAL-TM_Syll2012 Exam! ExamDiscuss.com now offer the newest CTAL-TM_Syll2012 exam dumps, the ExamDiscuss.com CTAL-TM_Syll2012 exam questions have been updated and answers have been corrected get the newest ExamDiscuss.com CTAL-TM_Syll2012 dumps with Test Engine here:
Test Management You are the Test Manager on a project following an iterative life-cycle model. The project should consist of nine iterations of one month duration each. It is planned to develop the most important features to have a stable core of the application in the first three iterations and to add the additional features in the last six iterations. At the beginning of the first iteration, only a draft version of the requirements specification document for the core features is available. Assume that during each of the first three iterations, the chosen features are fully completed and unit tested. Which of the following statements is true in this context?