Valid CTAL-TM_Syll2012 Dumps shared by ExamDiscuss.com for Helping Passing CTAL-TM_Syll2012 Exam! ExamDiscuss.com now offer the newest CTAL-TM_Syll2012 exam dumps, the ExamDiscuss.com CTAL-TM_Syll2012 exam questions have been updated and answers have been corrected get the newest ExamDiscuss.com CTAL-TM_Syll2012 dumps with Test Engine here:
Test Management In the next two months some new features will be constantly added to new releases of a project you are working on as Test Manager. You have identified as one of the main project risks, that the requirements specification will still be incomplete when your team starts the test design and implementation phase. Some requirements will most likely be completed too late to allow a proper test preparation. You and your test team have already worked on several similar past projects in the same organization. Which one of the following options would you expect to be the most effective at mitigating this risk?