Valid CISA Dumps shared by ExamDiscuss.com for Helping Passing CISA Exam! ExamDiscuss.com now offer the newest CISA exam dumps, the ExamDiscuss.com CISA exam questions have been updated and answers have been corrected get the newest ExamDiscuss.com CISA dumps with Test Engine here:
When performing an audit of a client relationship management (CRM) system migration project, which of the following should be of GREATEST concern to an IS auditor?
Correct Answer: C
Explanation/Reference: Explanation: Major system migrations should include a phase of parallel operation or a phased cut-over to reduce implementation risks. Decommissioning or disposing of the old hardware would complicate any fallback strategy, should the new system not operate correctly. A weekend can be used as a time buffer so that the new system will have a better chance of being up and running after the weekend. A different data representation does not mean different data presentation at the front end. Even when this is thecase, this issue can be solved by adequate training and user support. The printing functionality is commonly one of the last functions to be tested in a new system because it is usually the last step performed in any business event. Thus, meaningful testing and the respective error fixing are only possible after all other parts of the software have been successfully tested.