An IS auditor is assigned to audit a software development project which is more than 80 percent complete, but has already overrun time by 10 percent and costs by 25 percent. Which of the following actions should the IS auditor take?
Correct Answer: D
Explanation/Reference: Explanation: Before making any recommendations, an IS auditor needs to understand the project and the factors that have contributed to making the project over budget and over schedule. The organization may have effective project management practices and sound ITgovernance and still be behind schedule or over budget. There is no indication that the project manager should be changed without looking into the reasons for the overrun.