Valid CISA Dumps shared by ExamDiscuss.com for Helping Passing CISA Exam! ExamDiscuss.com now offer the newest CISA exam dumps, the ExamDiscuss.com CISA exam questions have been updated and answers have been corrected get the newest ExamDiscuss.com CISA dumps with Test Engine here:
Which of the following is MOST appropriate to review when determining if the work completed on an IT project is in alignment with budgeted costs?
Correct Answer: B
EVA is a project management technique that measures the performance of a project by comparing the actual work completed, the actual costs incurred, and the planned costs for the work scheduled. EVA can help determine if the project is on track, ahead of schedule, or behind schedule, and if the project is under budget, over budget, or on budget. EVA can also help forecast the final cost and schedule of the project based on the current performance. References ISACA CISA Review Manual, 27th Edition, page 255 18. Project Completion - Project Management - 2nd Edition How to Measure Project Success | Smartsheet