Due to changes in IT, the disaster recovery plan of a large organization has been changed. What is the PRIMARY risk if the new plan is not tested?
Correct Answer: A
Explanation/Reference: Explanation: Choices B, C and D are all possible problems that might occur, and would cause difficulties and financial losses or waste of resources. However, if a new disaster recovery plan is not tested, the possibility of a catastrophic service interruption is the most critical of all risks.