A disaster recovery plan for an organization's financial system specifies that the recovery point objective (RPO) is no data loss and the recovery time objective (RTO) is 72 hours. Which of the following is the MOST cost-effective solution?
Correct Answer: D
Explanation/Reference: Explanation: The synchronous copy of the storage achieves the RPO objective and a warm site operational in 48 hours meets the required RTO. Asynchronous updates of the database in distributed locations do not meet the RPO. Synchronous updates of the data and standby active systems in a hot site meet the RPO and RTO requirements but are more costly than a warm site solution.