You are the business analyst for your organization and you are completing the manage requirements traceability process. You are tracking the requirements to determine how the requirements are interrelated with one another and with the actual delivery of the project scope. There are actually three reasons why the business analyst should trace requirements. Which one of the following is not one of the three reasons why trace requirements are useful?
Correct Answer: C
Explanation Quality control is a project management process that inspects the project deliverables for quality. Its goal is to identify defects so that corrective actions may be implemented. Answer A is incorrect. Requirements allocation is the process of assigning stakeholder and solution requirements to solution components and releases. Answer B is incorrect. Requirements coverage allows business objectives to be traced to business rules, data elements, and use cases to determine how they'll be accomplished in the project. Answer D is incorrect. Impact analysis allows the business analyst and the project manager to determine how a change in requirements can affect the other requirements in the solution scope.