You are the business analyst for a new project. Part of this project is for the project team to manually install new workstations through the company's campus. Based on your research you have determined that the project team can install 25 new workstations per hour. Since there is a fixed amount of time that these workstations need to be installed you are considering adding additional labor for the implementation. You are also considering to adjust the prioritization of the project requirements based on the amount of workstations the project team can install per hour. What does the 25 workstations per hour represent in this scenario?
Correct Answer: D
Explanation Timeboxing describes the amount of work that the project team is capable of completing in a set period of time. Answer B is incorrect. Planning is a generic project management process that plans for the project work.