Valid IIA-CIA-Part3 Dumps shared by ExamDiscuss.com for Helping Passing IIA-CIA-Part3 Exam! ExamDiscuss.com now offer the newest IIA-CIA-Part3 exam dumps, the ExamDiscuss.com IIA-CIA-Part3 exam questions have been updated and answers have been corrected get the newest ExamDiscuss.com IIA-CIA-Part3 dumps with Test Engine here:
With regard to project management, which of the following statements about project crashing is true?
Correct Answer: D
Comprehensive and Detailed In-Depth Explanation: Project crashing is a schedule compression technique used in project management to shorten the project duration without altering the project scope. This is achieved by allocating additional resources to critical path activities, thereby reducing their completion time. While this approach can lead to increased costs due to the added resources, it helps in meeting tight deadlines. It's important to note that crashing focuses on accelerating project timelines by adding resources, not by changing the sequence of activities (as in fast-tracking) or by reassessing project requirements. However, project crashing can increase risks and may lead to rework if not managed carefully.