Valid IIA-CIA-Part2 Dumps shared by ExamDiscuss.com for Helping Passing IIA-CIA-Part2 Exam! ExamDiscuss.com now offer the newest IIA-CIA-Part2 exam dumps, the ExamDiscuss.com IIA-CIA-Part2 exam questions have been updated and answers have been corrected get the newest ExamDiscuss.com IIA-CIA-Part2 dumps with Test Engine here:
In the following risk control map risks have been categorized based on the level of significance and the associated level of control. Which of the following statements is true regarding Risk C?
Correct Answer: C
In the risk control map, Risk C is positioned in the upper left quadrant, indicating it is critical (high risk significance) but with a low level of control. This suggests that the current controls are insufficient to mitigate the high level of risk associated with Risk C. For critical risks, a higher level of control is necessary to ensure that the risk is properly managed and mitigated. References: * "Internal Auditing: Assurance & Advisory Services" (The Institute of Internal Auditors) * "Risk Management Framework" (COSO)