An architect is proposing a solution that has two HPE Moonshot 1500 chassis, each of which is full of m700 cartridges. The customer needs the solution to quickly deploy the OS to cartridges, back up a golden node image. and clone the image.
The customer is concerned about cost and is not interested in managing or monitoring performance of the solution,
Which solution meets these requirements?

Recent Comments (The most recent comments are at the top.)

jim - Aug 03, 2018

A. CMU is correct as the icsp is an alternative but more expensive because it can monitor and manage which is not needed in this solution.

LEAVE A REPLY

Your email address will not be published. Required fields are marked *

Question List (56q)
1 commentQuestion 1: Which statement describes the availability metrics for an HP...
Question 2: DRAG DROP Select all that apply. Click and drag the Network ...
Question 3: A customer has HPE BladeSystem BL460c Gen9 blades with two p...
Question 4: How does the HPE c7000 BladeSystems use of network infrastru...
Question 5: A customer requests a proposal for an HPE Apollo 4530 system...
Question 6: An architect is planning an HPE Moonshot System solution to ...
1 commentQuestion 7: An architect is planning an HPE Moonshot System deployment. ...
Question 8: A customer plans to purchase some c7000 blade enclosures equ...
Question 9: What is a basic assumption for an architect using the HPE Se...
Question 10: A customer needs an HPE Apollo 6000 solution and Remote Dire...
Question 11: An architect proposes an HPE Moonshot server solution for a ...
Question 12: A customer needs a live transcoding solution that meets the ...
Question 13: A customer is planning to migrate from a Virtual Connect Ent...
1 commentQuestion 14: An architect is planning an HPE Moonshot System to host a cu...
Question 15: An architect is planning an HPE Moonshot solution with m710p...
Question 16: An architect is proposing an HPE Moonshot System, including ...
Question 17: An architect reviews an HPE Apollo 6000 design and finds tha...
Question 18: View the Exhibit. (Exhibit) Refer to the exhibit. A customer...
1 commentQuestion 19: An architect has selected the FlexibleLOM option fur HPE XL2...
2 commentQuestion 20: An architect is designing an HPE Apollo 6000 solution to sup...
Question 21: A customer needs a server infrastructure update for its Hado...
Question 22: An architect needs to demonstrate the financial advantages o...
1 commentQuestion 23: Which discussion point describes a Tier I approach to datace...
Question 24: A customer needs to streamline monitoring to its HPE Apollo ...
1 commentQuestion 25: An architect proposes an HPE Moonshot 1500 chassis with m710...
Question 26: A customer plans to use Insight Control server provisioning ...
Question 27: An architect explains a software-defined data center (SDDC) ...
Question 28: A customer has an HPE Integrity Superdome X system with an n...
Question 29: An architect finds several vulnerabilities with a customer's...
1 commentQuestion 30: An architect is proposing a solution that has two HPE Moonsh...
Question 31: An architect needs to design a solution for a customer that ...
Question 32: A customer needs a hosted physical desktop solution. Users w...
1 commentQuestion 33: A customer is considering upgrading from a BL460c Gen8 to a ...
Question 34: An architect is writing a response to a Request for Proposal...
1 commentQuestion 35: An architect is planning an HPE Integrity Superdome X soluti...
1 commentQuestion 36: A customer has a mixed environment based on the G6, G7, Gen8...
Question 37: A customer has a large Oracle-based ERP solution that runs o...
Question 38: What defines lease rate factor (LRF)?...
Question 39: Which factors must the architect consider to help define an ...
Question 40: A customer is planning a multi-threaded HPC solution that wo...
1 commentQuestion 41: A customer needs high performance computing (HPC) and a smal...
Question 42: An architect is determining the amount of memory to propose ...
Question 43: Which of the HPE Transformation Areas should the architect d...
Question 44: A customer has 1,000 virtual machines that run on VMware ESX...
Question 45: A customer is deploying HPE Apollo Systems, which the custom...
Question 46: A customer recently purchased an HPE Moonshot chassis to hos...
Question 47: A software development customer's data center has servers fr...
Question 48: An architect is choosing between 1GbE and 10GbE connectivity...
Question 49: During a data center transformation discussion, an architect...
Question 50: A customer has an HPE Integrity Superdome X solution. The cu...
Question 51: An architect is designing a data center solution that contai...
Question 52: An architect takes the following notes during a meeting with...
Question 53: An architect is designing an HPE Apollo 6000 solution to sup...
Question 54: A customer has a Hadoop big data and analytics solution. The...
Question 55: An architect plans to propose a solution and illustrate how ...
Question 56: A customer's Gen9 web server resides behind a firewall. What...