During a Sprint Planning, a team has picked three User Stories: Story 1 - 5 Story Points Story 2 - 8 Story Points Story 3 - 3 Story Points At the end of the Sprint, the team has completed Story 1 and Story 3 and the Product Owner accepts these. The team has almost completed Story 2 but there are a few bugs identified in acceptance tests. What is the Velocity of this team?